Completed Railway Surveys in NER

 

(as received from Ministry of Railways in January, 2012)
PETS: Preliminary Engineering cum Traffic Survey
RETS: Reconnaissance Engineering cum Traffic Survey

 

Completed Railway Surveys in NER
Sl. No. Type of Survey Survey State Prog. Present status Target
1. PETS New Line from Dullabcherra to Cheraji (17.6 Km) including Gauge Conversion of Baraigram-Dullabcherra (29.4 Km) Assam 100% Project sanctioned in 2011-12. June'10
2. PETS New Line from Chaparmukh to Dibrugarh (340.36 Km) Assam 100% Updating of survey sanctioned in 2010-11. Survey completed and report submitted to Rly Board on 6.12.10. Nov'10
3. RETS (Updating) New Line from Barpeta Road-Tihu (57.8 Km) Assam 100% Updating of survey sanctioned in 2010-11. Updating of  survey completed and Report submitted to Rly Board on 2.9.10. Aug'10
4. RETS (Updating) New Line from Sarthebari to Changsari (59.85 Km) Assam 100% Updating of survey sanctioned in 2010-11. Updating of  survey completed and Report submitted to Rly Board on 7.10.10. Sept'10
5. RETS (Updating) New Line from Tuli to Tuli Town(9.15 Km) Nagaland 100% Updating of survey sanctioned in 2010-11. Updating of survey completed and Report submitted to Rly Bd on 30.7.10. Jul'10
6. RETS (Updating) New Line from Amguri  to Nagnimora (29.35 Km) Assam & Nagaland 100% Updating of survey sanctioned in 2010-11. Survey completed and Report submitted  to Rly Board on 30.12.10. Nov'10
7. PETS (Updating) New Line from Murkongselek to Pasighat (30.617 Km) Assam & Arunachal Pradesh 100% Project sanctioned in 2011-12 Pink Book. Apr'10

 

Page Maintained By: 