Projects

Bodoland Territorial Council (BTC)

(as in April, 2012)

 

 

A. BTC Package of Rs. 500 crores

 

(Rs. in Lakh)

 

Bodoland Territorial Council
Sl. No. Project Approved Cost Funds Released Funds Utilised Date of Last release Status
2004-05
1. Improvement of Dhamdhama Tupalia Subankhata Road 1372.00 1372.00 1331.57 14.03.2007 31.03.09 Completed
2. Improvement of Kaurbaha-Nagrijuli Road by metalling and black-topping including conversion of SPT Bridges into RCC Minor Bridges. 1450.00 1445.50 1407.73 15/04/2008 31.03.09 Completed (25.11.10)
3. Metalling and Black-topping of Narabari Dawkibari Road (Narabari to Florican Garden via Malgaon) 1595.00 1595.00 1538.10 31.03.09 Completed
4. Improvement of North Kajolgaon Dangtol Road 592.67 592.67 592.50 31.03.09 Completed
5. Improvement of Bhowraguri Kachugaon Road in Kokrajhar 2373.45 2373.45 2246.34 31.03.09 Ongoing
6. Improvement and upgradation of Kashikotra to Basugaon Road 550.69 550.69 534.65 31.03.09 Completed
7. Improvement of Sundari Bidyapur via Kakragaon Road 921.36 921.36 894.54 31.03.09 Completed
8. Metalling and backtopping of Gossaigaon to Saraibil Road including improvement of existing hard crust and conversion of STP bridge to Rcc bridges 1939.00 1939.00 1791.82 31.03.09 Ongoing
9. Widening and Strengthening of Fakiragram-Serfanguri Road including conversion of STP bridge 2049.16 2049.16 1947.00 31.03.09 Completed
10. Improvement of North Kajolgaon Bengtol Sonitpur road, Chirang 810.00 810.00 786.66 31.03.09 Completed
11. Construction of Road from NH-31 at Barama to Masalpur, Baska 1443.00 1086.00 1173.85 31.03.09 Ongoing
12. Improvement of Jalah Rupahi Saudarbhitha Gobardhana road, Baska 1000.00 1000.00 794.89 31.03.09 Ongoing
13. Improvement of Udalguri Bhakatpara road via Bhairaguri, Udalguri 444.00 444.00 433.47 31.03.09 Completed
14. Improvement of Barnagaon Pakribari road, Udalguri 150.00 150.00 146.38 31.03.09 Completed
15. Improvement of Kalaigaon Kundarbil road, Udalguri 132.00 132.00 128.96 31.03.09 Completed
16. Construction of 100 bedded Hospital at Kajalgaon in BTC area of Assam 3851.61 3851.61 3851.61 31.03.09 Completed
17. Kokrajhar Water Supply Scheme, Kokrajhar 2312.00 2312.00 2250.90 31.03.09 Ongoing
18. Construction of Bodofa Cultural Complex at Kokrajhar 1844.00 1844. 00 1350.00 8.03.10 Ongoing
2005-06
19. Champamati Irrigation Project 4385.00 4385.00 4385.00 31.03.09 Completed
20. Renovation/Re-construction of RNB Civil Hospital at Kokrajhar 758.09 758.09 602.32 31.03.09 Ongoing
21. Subankhata Water Supply Scheme 327.63 327.63 255.00 31.03.09 Ongoing
22. Sukla Irrigation Project 812.72 812.72 812.72 31.03.09 Completed
23. Goreswar to Khoirabari Road 657.28 657.28 638.15 31.03.09 Completed
24. Bhergaon-Chouni-Khagrabari-Dimakuchi Road 131.61 131.61 131.61 31.03.09 Completed
25. Lailongpara-Kopati Road Via Boro Bazar 131.05 131.04 127.23 31.03.09 Completed
26. Khowrang Mahanpur Road 250.00 250.00 246.29 31.03.09 Completed
27. Chapaguri-Khagrabari Road 630.00 630.00 624.69 31.03.09 Completed
28. Tulsijhyora-Kailamaila Road via Amguri 900.00 900.00 887.74 31.03.09 Completed
29. Bijni-Panbari Road 1558.58 1558.58 1261.88 31.03.09 Ongoing
30. Gossaigaon to Kazigaon via Bhukka, Tipkai Road 1100.00 1100.00 876.78 31.03.09 Ongoing
31. Construction of Cold Storage at Udalguri district 413.66 413.65 413.65 31.03.09 Completed
32. Construction of Cold storage at Kokrajahar district 413.66 413.65 413.65 31.03.09 Completed
33. Construction of North East Gate Way Bus Terminus at Srinwgai Gossaigaon 144.42 144.42 140.38 31.03.09 Completed
34. Improvement of Tihu Doomni Road leading to Indo-Bhutan foot hills from 7th to 25 km in Baska district 995.00 995.00 965.99 31.03.09 Completed
35. Improvement of Khoirabari MPK road (Andherighat) to Harisinga via Bhergaon, Tangla and Purandia 42.25 km length with conversion of 11 SPT bridges to RCC 2650.26 2650.26 2209.34 31.03.09 Ongoing
36. Construction of Kashikotra Bamungaon Bengtol Road 1169.00 1169.00 966.32 31.03.09 Ongoing
2006-07
37. Bheragaon Piped Water Supply Scheme 246.63 241.30 245.69 2.02.10 Completed
38. Udalguri Piped Water Supply Scheme 533.70 254.20 254.20 31.03.09 Ongoing
39. Uttarpar Piped Water Supply Scheme 864.39 822.82 855.83 2.02.10 Completed
2008-09
40. Improvement of Jalah to Kumarikata Road including 2 bridges over River Kaldia and Dirring 2121.20 1060.60 273.00 08.10.10 Ongoing
41. Conversion of SPT Bridge 20/1 over River Gangia into RCC Bridge on Gosaigaon Sapatgram Road in Kokrajhar District 1082.68 541.34 200.00 2.03.09 Ongoing
42. Strengthening of 11 Kv HT & LT Line with 12 Meter Steel Tubular Pole including illumination of Kokrajhar Town 520.29 260.14 0.00 2.03.09 Ongoing

 

Total 47626.79 45076.77 40988.43    
 

 


B. Additional BTC Package of Rs. 250 crores

 

(a) Projects Sanctioned by Ministry of DONER

 

(Rs. in Lakh)

 

Sl. No Project Approved Cost   Amount Released Amount Utilised Date of Release Status
1 Up-gradation of Sports Complex at Kajalgaon in Chirang (Chirang) 500.00 250.00 0.00 10.01.11   Ongoing
2 Construction of Cold Storage at Barama (Baksa) 890.00 445.00 0.00 10.01.11   Ongoing
3 Setting up of Integrated Agro-Processing Park at Lalpool (Udalguri) 907.00 453.50 0.00 10.01.11   Ongoing
4 Enhancement of existing facility in Veterinary Hospital at Titaguri (korajhar), Samthaibari (chirang) and Bornagaon in Udalguri District. 901.90 450.95 0.00 21.04.11 Ongoing
5 Construction of RCC Bridge No. 8/1 over Gurufella river on Gossaigaon-Sapatgram Road (Kokrajhar) 792.00 396.00 0.00 14.12.10   Ongoing
6 Construction of RCC Bridge No. 6/3  over Gongia river on Dotma-Bhawraguri Road (Kokrajhar) 800.00 400.00   0.00 14.12.10   Ongoing
7 Construction of RCC Bridge No. 3/1 over Puthimari river at Dolonghat (Dhulabari) (Baksa) 800.00 400.00 0.00 14.12.10   Ongoing
8 Bodoland Bhawan at Dwarka, New Delhi 909.83 454.92 0.00 10.01.11 Ongoing
9 Proposed Integrated Textile Park at Kharuajan, Mushalpur. 4100.00 2050.00 0.00 21.04.11   Ongoing
10 Bodo Language Research and Development Centre for Gauhati University, Kokrajhar. 295.81 147.90 0.00 21.04.11 Ongoing
11 Setting up of Model Dairy, Fishery, Horticulture, Poultry Farm Training Centre at Kokalibari Baksa District. 1146.00 500.00 0.00 20.03.12 Ongoing
12 Construction of Khanda Road from Dawdhara to Doomni via Nawputa in Baksa District. 1075.00 469.30 0.00 20.03.12 Ongoing
13 Improvement of Road from Bashbari to Gossaigaon via Dingdinga in Kokrajhar Dist. 2500.00 1091.00 0.00 20.03.12 Ongoing
14 Improvement of Bishmuri-Saralpara Sarbhanga Rd. in Kokrajhar Dist. 2679.00 1169.00 0.00 20.03.12 Ongoing
15 Metalling and Blacktopping of Road from Lalmati to Manglajhora in Kokrajhar Dist. 600.00 261.83 0.00 20.03.12 Ongoing
  Total 18896.54 8939.40      
 

 

 

(b) Projects Pending Sanction by Ministry of DONER for want of approval of State Level Standing Committee (SLSC) of Government of Assam

 

(Rs. in Lakh)

 

Sl. No Project Indicative Cost
1 Setting up of IT Park – Kokrajhar 2594.21
2 Setting up of Food Processing Plant at Karigaon (Kokrajhar) 996.00
3 Improvement of Rowta Station Feder road 133.00
4 Construction of road from Borobazar to Ulubari via Bagargaon including RCC Bridge & cross Drainage in Chirang District. (Subject to environmental clearance from the Forest Department) 1700.00
  Total 5423.21