SARDP-NE

Maps

 

 

Introduction

 

Brief Status of SARDP-NE

(Source: M/o Road Transport & Highways)
(as in March, 2012)

 

 

  1. The Ministry of Road Transport & Highways has initiated mega road development programme in North East with name "Special Accelerated Road Development Programme in North East (SARDP-NE)".The scope of the programme has been enlarged from time to time, since September. 2005. As on date Government has given approval for 2/4 laning of 6418 km of various categories of roads under Phase 'A' and Arunachal Package of SARDP-NE in entire North East at an estimated investment of about Rs 33.500 crore. Apart from the above Government has also given approval to preparation of detailed project report for 3723 km of roads under Phase 'B' so as to enable Government to plan expenditure on these roads during next 5 years plans.
  2. Apart from SARDP-NE National highways Authority of India is implementing the 4 laning of 672 km of East West Corridor from Srirampur (Assam/ W. Bengal border) to Silchar in Assam at an estimated cost of Rs 6000 crorc and 2 laning with paved shoulders from Jowai to Rattecherra (104 km) in Meghalaya under NHDP-III.
  3. As seen from the above an amount of about Rs 40,000 crore for massive road infrastructure development has been committed by the Government for North East. These programmes once implemented fully will change the face of the North Eastern States.
  4. Objectives of SARDP-NE:

 

  • Upgrade National Highways connecting State Capitals to 2/ 4 lan
  • To provide connectivity of all 88 District Headquarter towns of NER by at least 2- lane road;
  • Improve roads of strategic importance in border area.
  • Improve connectivity to neighboring countries

 

5. The SARDP-NE programme has been divided into 3 parts:

 

(i) Phase 'A

(ii) Arunachal Pradesh Package of Roads and Highways (Arunachal Package)

(iii) Phase ‘B’

 

6. Details of approvals:

(Rs in crore)

Details of approvals
Phase Length(km) approved
Approved for execution Approved ‘in-principle’ Approved for DPR preparation Total approved
Length

 

(km)

Estimated

 

cost

Length

 

(km)

Estimated cost Length

 

(km)

Estimated cost Length

 

(km)

Estimated cost
Phase ‘A’ 3213 12821 886 8948 - - 4099 21769

Arunachal  Package

2319 11703 - - - - 2319 11703
Phase ‘B’ - - - - 3723 64 3723 64
Total 5532 24524 886 8948 4825 64 10141 33536

 

7. The State wise distribution of roads under the 3 parts is as under:

 

The State wise distribution of roads under the 3 parts is as under
STATE SARDP-NEPhase 'A' Arunachal Package SARDP-NEPhase 'B' Grand Total

NHs

SR/ GS

Total

NH

SR/ GS/ Strtg

Total

NH

SR/ GS/ Strtg

Total

NH

SR/ GS/ Strtg

Total

Arunachal Pradesh 52 212 264 1346 835 2181 0 931 931 1398 1978 3376
Assam 1179 177 1356 126 12 138 0 285 285 1305 474 1779
Manipur 39 166 205 0 0 0 0 202 202 39 368 407
Meghalaya 259 526 785 0 0 0 161 201 362 420 727 1147
Mizoram 221 100 321 0 0 0 416 272 688 637 372 1009
Nagaland 81 350 431 0 0 0 622 169 791 703 519 1222
Sikkim 80 505 585 0 0 0 0 68 68 80 573 653
Tripura 130 22 152 0 0 0 86 310 396 216 332 548
Total 2041 2058 4099 1472 847 2319 1285 2438 3723 4798 5343 10141

 

SR: State roads; GS: General Staff roads Strtg: Strategic roads

 

8. Status of the SARDP-NE programme

 

1. Phase 'A' of SARDP-NE

 

Phase 'A' involve improvement/ construction of 4099km of roads (2.041 km NH and 2058 km State roads and other roads) at an estimated cost of Rs.21,769 crore. Out of these 3325km roads, has been approved for execution and balance 774 km has been approved 'in- principle'.

 

The implementation of these roads has been entrusted to various Agencies such as State PWDs, BRO and NHAI. So far, 2391km roads at Rs 10,186 crore under SARDP-NE Phase 'A' have been sanctioned/awarded and 385 km @ Rs 2683 crore are under process of approval/tendering/ examination. The likely target date of completion for sanctioned road stretches of Phase A' is March 2015.

 

2. Arunachal Pradesh Package of Roads and Highways.

 

Under this package 776 km road stretches were approved on Hybrid HOT (Annuity) basis. Tenders for all 4 sub-projects of 774 km (revised length) have been awarded at total project cost(TPC) of Rs 5111 crore.

 

Road stretches aggregating to 1543 km length have been approved for execution on Cash contract basis. Out of these, about 547 km length has been sanctioned/awarded amounting to Rs 2699 crore, till date.

 

The total sanctions accorded is for 1322 km roads at Rs 7810 crore and 79 km (a), Rs 354 crore are under process of approval/examination. The entire Arunachal Pradesh Package is targeted for completion by March, 2017.

 

(iii) Performance of SARDP-NE.

 

(as in April, 2012)

 

Performance of SARDP-NE
Year Sanctions/ Award Length completed (km) Financial (Rs. Crore)
Length (km) Cost
(Rs in crore)
Allocation Expenditure
2006-07 501 1285 Preliminary 550 450
2007-08 240 615 150 700 652
2008-09 187 835 290 1000 637
2009-10 188 1070 156 1200 676
2010-11 1615 9439 146 1500 1065
2011-12 992 4752 150 1950 1940
Total 3723 17996 892 6900 5420

 

Total approval of SARDP-NE is for 3616 km (a) Rs 17,568 crore, till date.

 

9. Status of allocation and expenditure

 

(Rs.in crore)

 

Status of allocation and expenditure
Year Allocation Expenditure/Release Total
BRO State PWDs NHAI  
2006-07 550 108.00 47.51 294.00 449.51
2007-08 700 222.00 135.74 294.00 651.74
2008-09 1000 389.00 248.25 - 637.25
2009-10 1200 387.23 288.68 - 675.91
2010-11 1500 410.00 657.28   1067.28
2011-12 1600 - - - 1421
Grand Total 6550       2997.85 (45.77%)

 

 

Year Sanctions/Award  (KM) Length Completed (KM)
2006-07 501 Preliminary
2007-08 240 150
2008-09 187 290
2009-10 188 156
2010-11 1615 146
2011-12 983
(as on 23.3.2012)
60
(as on 31.12.2011)
Total 1314 802

 

10. Length awarded and constructed:

  • Total length approved – 3616 km @ Rs.17, 568 crore till date.
  • Total length awarded – 1314 km
  • Total length constructed – 802 km
  • Target for award in 2011-12  - 1991 km
  • Target for completion in 2011-12  - 270 km

List of Roads

 

Ministry of Road Transport and Highways
Special Accelerated Road Development Programme for North East (SARDP-NE) [PDF]
(195.49 KB)

 

 

Maps

 

Major Road Development Programmes in North East Region

 

Roads Covered for improvement in Arunachal Pradesh under SARDP-NE

 

Map of Major Road Programmes[PDF](368.53 KB)