Roads from NLCPR

Non-Lapsable Central Pool of Resource (NLCPR) Scheme

 

Roads & Bridges Sector

 

Releases & Utilisation

 

(As on March, 2012)

 

(Rs. in Lakh)

 

Roads from NLCPR (Roads & Bridges Sector)
Sl. No. NLCPR Project Date of Sanction Approved cost Total Release Total utilisation %age Utilisation Date of Completion
Arunachal Pradesh
1. Improvement/ Construction of Road from Sagalee to Sakiang (50 Km) 17/02/2006 4288.70 3755.14 3489.75 93 % -
2. Construction of Steel Suspension Bridge over Subansiri river near Siyum (Span 174.00 Mtr) 17/02/2006 1308.00 1158.13 775.45 67 % -
3. Improvement of Palizi – Thrizino Road (17.00 Km) 17/02/2006 743.90 669.51 645.81 96 % -
4. Construction of road from Pakke to Wai (18.00 Km) 17/02/2006 1335.41 1166.86 1000.65 86 % -
5. Improvement and realignment of Porter Track from Jhang to Sulungthi (95 KMs) 28/10/2002 255.00 255.00 255.00 100 % 01/06/2007
6. Construction of porter Track from Nuranang to Mago 15/01/2004 259.00 255.00 255.23 100 % 18/10/2006
7. Maintenance of Foot track and Sustension Bridges 22/03/2000 100.00 100.00 100.00 100 % 28/02/2004
8. Construction of Motorable Suspension Bridge over river Siang at the site of Gandhi Bridge 27/03/2006 4843.00 2541.89 1377.71 54 % -
9. Improvement/ Upgradation of Menga-Giba Road (8 Km) 27/03/2006 356.67 321.00 240.75 75 % -
10. Improvement of Porter Track from Tungri to Mago (70 Km) 27/12/2005 310.56 271.36 271.36 100 % -
11. Construction of Steel Suspension Bridge over Siang River and approach roads at Kodak near Tuting 27/12/2005 3894.00 1219.82 1219.82 100 % -
12. Construction of road from Dipulamgu bridge point to Pipu (14 Km) 27/12/2005 417.20 364.54 279.62 77 % -
13. Construction of road from Bameng to Lada (40 Km) 27/12/2005 890.19 777.83 515.00 66 % -
14. Construction of Motorable Suspension Bridge over River Lohit to connect Manchal Administrative Circle (Span 156.55 m) 27/12/2005 1309.79 1144.48 825.18 72 % -
15. Construction of link road from Lhou Nallah to Mukto Circle HQ. via Mirba, Gomkelling and Serjong (15 Km) in Tawang District 27/12/2005 1802.97 1575.41 1295.31 82 % -
16. Improvement of Doimukh Toru Road 40 Km. (from NH-52A) Nirjuli to Sagalee 27/12/2005 2186.90 1914.52 1647.90 86 % -
17. Construction of road from Jengging to Ramsing in Upper Siang District (35 Km) 25/09/2006 536.62 482.96 369.04 76 % -
18. Construction of bridge over Siyom on Kaying to Paksing road (Span 122.00 mtr.) 06/12/2006 763.82 667.41 667.41 100 % 28/02/2011
19. C/o road from Nafra to Nakhu and Nachiban in West Kameng District (11 Km) 26/03/2007 754.01 678.61 678.64 100 % -
20. Construction of Road from NH 52 'A' to Pappu Hill Settlement (2 Km) 28/06/2007 398.99 125.68 125.68 100 % -
21. C/o road from Nyorak to Rime Moku village in West Siang District (20 Km, Ph-I – 9.20 km) 28/06/2007 989.75 890.78 639.49 72 % -
22. C/o road from Jop to Silsango in Lower Subansiri District (30 Km) 28/06/2007 3449.52 3011.01 3011.00 100 % -
23. Construction of Motorable Suspension Bridge over river Siang between BRTF road & Komsing village (Span 225 m) at Sangam point in East Siang District 26/09/2007 1834.41 1229.88 577.84 47 % -
24. C/o road from Sille to Yagrung in East Siang district. (10KM) 16/11/2007 500.94 334.60 334.60 100 % -
25. Construction of Bailey Bridge (Steel Built-up Girder Bridge) between Namara and many other villages under Seijosa circle 31/12/2007 854.12 269.05 20.60 8 % -
26. C/o road from Dumporijo to Hali (45 Km) 27/03/2008 3176.36 2802.67 2101.99 75 % -
27. Construction of Satnaguri to Longding road via Kanubari, Banfera, Wanu and Zedua (Phase-I) – (15.50 Km) 26/03/2008 565.75 499.19 499.19 100 % -
28. Construction of Gacham – Morshing Road (24.50 Km) 15/09/2008 1962.49 1731.61 1310.80 76 % -
29. Construction of Wak Liromoba Road (78 Km) – Phase – I (15 Km) 15/09/2008 660.04 582.39 436.00 75 % -
30. Construction of Road from New Mohong to Mahadevpur Township via Nongkhon (12 Km) 15/09/2008 355.40 313.59 218.39 70 % -
31. Construction of Road from Changlang to Khimiyang (36.10 Km) 15/09/2008 858.70 757.67 557.16 74 % -
32. C/o road from Hawai to Manchal Bridge point (55.77 KM) 08/10/2008 3252.92 1024.67 1024.67 100 % -
33. Construction of Tamen-Tali road via Yirkoum (60 KM) – Phase-I 0-49 Km 24/12/2008 898.11 792.45 792.45 100 % 31/03/2011
34. Construction of road from Sangram to Phassang-Pallang via Nyapin (SDO HQ) – Phase-I 24/12/2008 881.72 777.99 546.55 70 % -
35. Improvement & Extension of Dosing, Pareng, Sine, Yibuk, Liging road. (Phase-I) 30/03/2009 1826.08 1231.51 575.21 47 % -
36. Construction of road from Kheti to Dadam (21 KM) 30/03/2009 1087.08 725.19 725.19 100 % -
37. Restoration and upgradation of 32 KM internal road at Ziro Township 28/03/2009 1399.97 1235.26 935.99 76 % -
38. C/o road from BRO road (4 KM point) on Anini Dambuine road to Etabe (12 KM) 28/03/2009 2213.96 697.40 404.87 58 % -
39. Construction of Single lane bailey bridge (span 40 mtr) over Tasing river in between Borguli village and Seram in East Siang district 28/03/2009 340.37 229.56 107.21 47 % -
40. Road from Magopam to Bichom via Namfri (50 KM) via Ditching, Sacheda, Ramu-Sotu and Lichini under Singchung sub-division. 31/07/2009 1567.17 1382.79 1041.91 75 % -
41. Construction of road from 80 KM point on Kimin – Ziro BRTF road to Krishi Vigyan Kendra at Yachuli (5.50 KM) (Lower Subansiri) 11/01/2010 769.05 553.02 270.00 49 % -
42. Construction of Motorable Steel Arch Bridge over river Yamne at Reglat under Mariyang Division span 90 Mtr. 05/02/2010 634.39 228.38 0.00 0 % -
43. Construction of road from Jia tiniali on Roing shantipur road (Ch:9.20 Km) to Bizari via Idilli (19.80 Km) 05/02/2010 1544.61 1090.30 545.15 50 % -
44. Constrcution of Road from Pugging to Palling 15/02/2010 1530.19 540.07 104.00 19 % -
45. Improvement of Tawang Township road Network in Arunachal Pradesh 15/02/2010 489.64 348.64 172.82 50 % -
46. Construction of Road from PWD road from Kamhua Noknu Village (Pongchau Circle) to Nginu - BRTF Road point (Wakka Circle) in Tirap District 12/02/2010 1353.18 955.20 477.60 50 % -
47. Construction of road from J.N. College Pasighat to Balek, East Siang District 02/06/2010 500.26 172.49 0.00 0 % -
48. Construction of road from Loffa to Pakoti village (8 km) 14/06/2010 676.33 477.40 238.70 50 % -
49. Construction of Namsang - Khela Road (45.30) 29/12/2009 494.74 352.72 352.72 100 % -
50. Construction of RCC Bridge over river Kamphai under Wakro Circle (Span 80 mtr) 23/12/2010 608.10 214.00 0.00 0 % -
51. Construction of road from Darak to Belo to Yomcha 25/11/2010 980.81 352.96 0.00 0 % -
52. Construction of road from Lumba to Rayung via Gallang, Joru and Rissi villages (20 km), Phase 1 03/12/2010 2160.04 1553.86 776.93 50 % -
53. Construction of road from Pachi to Rigom via Fachang, Tabri Lochung and Bokar (33 km) 24/12/2010 1416.82 509.99 0.00 0 % -
54. Construction of road from Janam to Okhasun under Wakka Circle Hq. (19 km) phase 1 23/12/2010 1085.87 781.80 390.90 50 % -
55. Construction of road from Chambang to Phaa (30 km), Phase 1 23/12/2010 1179.22 424.46 424.46 100 % -
56. Construction of Steel Bridge over river Wome at Pakke point 25/11/2010 237.48 83.82 0.00 0 % -
57. Construction of road from Itanagar to Seijosa (86 km) [Phase 1: Road from Kampa to Tapiaso (30 km) 25/11/2010 4316.87 1551.75 0.00 0 % -
58. Construction of Bailey /RCC bridge over river Buche and Bah of Litemore-Taramori road, West Siang District 11/10/2010 300.00 108.00 108.00 100 % -
59. Construction of road from NH-153 Longbi village point to Tengman village via Khetwa and Jotin Juda (35.00 km) 28/02/2011 2133.60 767.86 0.00 0 % -
60. Improvement of Janagthung-Cherrong-Panchvati-Chhanda road, West Kameng District 28/02/2011 2510.17 1782.85 0.00 0 % -
61. Construction of road from 10 km point of Likabali-Aalo BRTF road to connect Kane village via Magi (7.5 km) 28/02/2011 1823.32 651.55 0.00 0 % -
62. Construction of road from Digi to Panimuri via Sinyumrijo 24/06/2011 369.24 131.95 131.95 100 % -
63. Upgradation of road from Subansari bridge point to Segi CO(HQ) 24/06/2011 1982.05 704.98 0.00 0 % -
64. Construction of road from Mahadevpur Town to Krishnapur Village Lekang Circle in Lohit District (4.5km) 27/06/2011 599.30 214.33 0.00 0 % -
65. Construction of Motorable Bridge over Siyom River to connect left bank at Paya (span 120m) in West Siang District 19/09/2011 968.53 341.83 0.00 0 % -
66. Construction of road from Rani to Oiramghat (Assam) via Sika Tode-Sika Bamin Village - Jampani and Anchalghat Camp road (25km) in East Siang District 19/09/2011 3325.47 1195.85 0.00 0 % -
67. Development of Pakke to Seppi Liya Road (22 km) in East Kameng District 23/09/2011 1598.75 574.63 0.00 0 % -
68. Upgradation of Namchik-Miao-M'Pen Road (37 km) 19/09/2011 2079.84 747.62 0.00 0 % -
69. Improvement and Upgradation of Internal Road at Daporijo township in Upper Subansari District 19/12/2011 534.69 188.71 0.00 0 % -
70. Construction of road from Magopam to Bichom via Namfri, Ditching, Sacheda, Ramu-Sutu and Uchini (Phase-II) in West Kameng District 28/12/2011 2052.43 735.76 0.00 0 % -
71. Construction of Wak Liromaba Road (78km) - [Phase-II: 0-26Km] in West siang District 23/03/2012 2280.18 0.00 0.00 0 % -
Total for Arunachal Pradesh (71 Projects) 97964.76 58301.19 35889.65    
Assam
72. Construction of RCC Bridge No. 1/1, 3/1 and 5/1 on Bahirjonai Berachapari Road in Dhemaji District (Assam) with approaches 21/02/2006 552.17 396.03 151.25 38 % -
73. Construction of RCC Bridge No. 1/1, 4/1 and 5/1 on Sripani Jengrai Road in Dhemaji District (Assam) with approaches 21/02/2006 301.78 95.06 95.06 100 % -
74. Recce of Road in BAC Area 31/10/2000 3.00 3.00 2.80 93 % 31/03/2005
75. Barpeta Basbari Road, Barpeta 31/10/2001 90.00 87.00 10.58 12 % -
76. Kachubari-Naokata-Patharighat Road, Nalbari & Darrang 31/10/2001 396.00 396.00 396.00 100 % 31/03/2004
77. Kumarikata- Jalah Road, Nalbari. 31/10/2001 1508.00 1496.40 1496.40 100 % 31/03/2005
78. Rowta- Udalguri Road, Darrang. 31/10/2001 832.00 832.00 832.00 100 % 31/03/2004
79. Tamulpur-Goreswar Road, Nalbari. 31/10/2001 473.41 473.41 473.00 100 % 31/03/2004
80. Udalguri - Kahibari road 31/10/2001 366.00 366.00 366.00 100 % 31/03/2004
81. Udalguri- Bhairabkunda Road, Darrang. 31/10/2001 586.00 586.00 586.00 100 % 20/01/2004
82. Ambagaon - Barigaon Road 18/02/2003 763.00 713.08 506.55 71 % -
83. Barangajuli-Khairabari road 18/02/2003 210.00 59.30 2.36 4 % -
84. Charuali - Nagarijuli Road 18/02/2003 538.00 492.30 563.07 114 % -
85. Hardutta-Birudatta road 18/02/2003 133.00 131.46 131.46 100 % 20/11/2004
86. Mangaldai- Bhutiachang Road, Darrang. 18/02/2003 120.70 120.70 120.70 100 % 20/12/2003
87. Rangiya Goreswar Road 18/02/2003 152.00 151.93 151.68 100 % 20/02/2004
88. tangla - Dimakuchi Road 18/02/2003 251.00 251.00 251.00 100 % 20/02/2005
89. Udalguri-Tamulpur Road, Darrang. 18/02/2003 3632.00 3345.99 2192.73 66 % -
90. Causeway Over Kulsi, Darrang 11/02/2004 100.00 100.00 0.00 0 % -
91. Chamuapara - Purandia Road 11/02/2004 485.00 281.09 236.89 84 % -
92. Construction of RCC Bridge No. 2/2 - Haripur Sansarghat Road in Nalbari District 20/02/2004 226.37 182.99 182.99 100 % 04/06/2009
93. Construction of RCC Bridge No. 20/1 - Nalbari Palla Road in Nalbari District 20/02/2004 144.36 113.74 113.74 100 % 31/07/2009
94. Construction of RCC Bridge No. 42/5 & 74/1 on DLHS Road in Karbi Anglong District 19/03/2004 143.25 112.57 112.66 100 % 12/11/2008
95. Jagun-Kharsang Road(11 KM) 24/12/2003 303.94 256.61 256.61 100 % 30/04/2007
96. Rcc Bridge on Additional Approach to Airport road(2nos) 24/12/2003 173.39 164.51 163.68 99 % 20/07/2007
97. Rcc Bridge on Mandakata North Guwahati Road(2 nos) 07/01/2004 240.19 189.17 189.17 100 % 20/05/2006
98. RCC Bridge 4/1 on Hatigaon -Betapara 07/01/2004 153.84 133.97 133.97 100 % 13/05/2010
99. Tangla - Deor Road 11/02/2004 379.00 0.00 0.00 0 % -
100. Udalguri - Kharupetia Road 11/02/2004 925.00 0.00 0.00 0 % -
101. Construction of Lay Byes and Bus Bays in Guwahati City for National Games 2005 20/01/2004 278.00 0.00 0.00 0 % -
102. Construction of RCC Bridge No. 1/2 and 3/1 on Sarupeta Bhuyapara in Barpeta District 30/09/2004 177.36 161.76 161.76 100 % 30/09/2009
103. Construction of RCC Bridge No. 1/3, 2/1 and 3/1 on Namti Ali in Sivasagar District 21/09/2004 89.68 81.55 81.55 100 % 17/08/2009
104. Construction of RCC Bridge No. 156/2, 159/1, 163/2, 165/3, 172/2, 174/2, 177/1 and 182/2 on Dhodar Ali Road in Sivasagar District 30/09/2004 352.51 321.25 321.25 100 % 18/02/2008
105. Construction of RCC Bridge No. 4/2, 9/2, 10/2 and 17/1 on Met Na-Ali Jorhat Titabor in Jorhat District 30/09/2004 142.60 130.39 130.33 100 % 31/03/2009
106. Construction of RCC bridge No.1/1, 2/1 and 2/2 on Jonnai Silapathar Road in Dhimaji District 29/07/2004 190.00 173.37 173.37 100 % 30/06/2006
107. Construction of RCC bridge No.1/2 on Manja to Hidim Teron Road in Karbi Anglong District 28/07/2004 178.12 162.38 62.04 38 % -
108. Construction of RCC bridge No.12/1 and 12/2 on Bangaon Jagara Road in Nalbari District 29/07/2004 174.81 159.50 159.90 100 % 08/06/2009
109. Construction of RCC bridge No.12/3 on Balkulia Rajapathar Road in Karbi Anglong District 28/07/2004 173.51 158.14 60.33 38 % -
110. Construction of RCC bridge No.13/1, 14/1, 15/1, 20/3 and 22/1 on Silchar Kumbhirgram Road in Cachar District 29/07/2004 567.87 517.52 517.52 100 % -
111. Construction of RCC bridge No.24/1 on Barpathar-Bokajan Deithor-Chowkihola (BBDC) Road in Karbi Anglong District 28/07/2004 54.42 49.00 48.87 100 % 30/03/2009
112. Construction of RCC bridge No.26/3 on Samar Ali Das Road in Karbi Anglong District in Assam 28/07/2004 167.54 153.34 58.63 38 % -
113. Construction of RCC bridge No.3/1, 3/2,6/3,6/4, 6/6,10/5,12/1, 13/1, 21/2 and 23/2 on Border Roads (Gar Ali) in Jorhat District 29/07/2004 397.56 362.84 362.84 100 % 30/11/2007
114. Construction of RCC bridge No.35/2 and 53/2 on Moran Naharkatia Road in Dibrugarh District 29/07/2004 114.16 104.20 84.23 81 % -
115. Construction of RCC Bridge No.4/3, 10/2 and 14/1 on Pengeri Philobari Road in Tinsukia District with approaches 07/07/2004 233.66 216.29 184.26 85 % -
116. Construction of RCC bridge No.40/1 on Bagals Road in Kamrup District 28/07/2004 128.88 117.32 117.32 100 % 31/10/2006
117. Construction of RCC bridge No.40/2 on CPDMDK Road in Karbi Anglong District 28/07/2004 131.82 120.27 46.70 39 % -
118. Construction of RCC Bridge No.6/1 on Udalguri Barbengera Road in Darrang District with approaches 08/07/2004 104.03 96.16 96.16 100 % 07/09/2007
119. Construction of RCC bridge No.8/2, 20/1, 21/1, 23/3, 29/2, 32/1, 36/1 and 40/1 on Mangaldoi Bhutiachang Road in Darrang District 29/07/2004 684.70 615.89 615.89 100 % 03/08/2009
120. Improvement of Bhangagarh - Bharalumukh VIP Road for National Games 2005 17/03/2005 982.80 892.99 892.99 100 % 30/09/2006
121. Improvement of Road between Hatigaon Bhetapara Road for National Games 2005 17/03/2005 456.26 414.67 414.67 100 % 31/01/2007
122. Kaithalkuchi-Barama Subankhata Road, North Kamrup 06/12/2001 61.00 61.00 61.00 100 % 04/02/2006
123. Namati-Masalpur Road, Nalbari 06/12/2001 31.00 31.00 31.00 100 % 30/06/2007
124. Tihu-Barama Road, Nalbari. 06/12/2001 64.00 64.00 64.00 100 % 15/04/2006
125. Tangla - Bhergaon Road 18/02/2003 0.00 0.00 0.00 0 % -
126. Diguncherra-Airport Road 01/04/1998 25.00 25.00 25.00 100 % 31/03/2000
127. Road from Jarighat to Lakhichhera. 28/03/2000 92.00 92.00 92.00 100 % 31/08/2002
128. Road from Hatichhera Dudpati Mudrennamukh. 28/03/2000 43.00 43.00 43.00 100 % 31/12/2001
129. Construction of RCC Bridge No.27/2, 28/1,29/1,30/2,32/2,35/1 and 45/1 including approaches on Dhubri-Kachugaon Road in Kokrajhar 16/05/2006 516.40 368.13 356.93 97 % -
130. Construction of RCC Bridge No. 1/1 and 4/1 with approaches on Nilbagan-Hojai Road in Nagaon District (Assam) 02/06/2006 191.67 170.79 170.79 100 % 30/07/2009
131. Construction of RCC Bridge No.3/1 including approaches on Pukia Silapathar Road in Dhemaji District. 16/05/2006 136.78 121.89 121.89 100 % 30/05/2008
132. Construction of RCC Bridge No. 4/1 and 15/1 including approaches on Nagaon - Bhuragaon Road in Nagaon District 16/05/2006 434.40 387.08 387.08 100 % 28/02/2011
133. Construction of RCC Bridge No.38/1, 43/1,43/3 and 44/2 including approaches and subway on Silchar - Hailakandi Road in Hailakandi District 16/05/2006 353.13 250.77 201.21 80 % -
134. Improvement of Kaurbaha-Nagrijuli Road by metalling and black-topping including conversion of SPT Bridges into RCC Minor Bridges (BTC Package) 31/12/2004 1450.00 1445.50 1407.73 97 % 25/11/2010
135. Metalling and Black-topping of Narabari Dawkibari Road (Narabari to Florican Garden via Malgaon)(BTC Package) 31/12/2004 1595.00 1595.00 1538.10 96 % 30/11/2009
136. Improvement of North Kajolgaon Dangtol Road (BTC Package) 31/12/2004 592.67 592.67 592.50 100 % 30/09/2008
137. Improvement of Bhowraguri Kachugaon Road in Kokrajhar (BTC Package) 31/12/2004 2373.45 2373.45 2246.34 95 % -
138. Improvement and upgradation of Kashikotra to Basugaon Road(BTC Package) 31/12/2004 550.69 550.69 534.65 97 % 31/08/2006
139. Improvement of Sundari Bidyapur via Kakragaon Road(BTC Package) 31/12/2004 921.36 921.36 894.54 97 % 30/09/2008
140. Metalling and backtopping of Gossaigaon to Saraibil Road including improvement of existing hard crust and conversion of STP bridge to Rcc bridges(BTC Package) 07/02/2005 1939.00 1939.00 1791.82 92 % -
141. Widening and Strengthening of Fakiragram-Serfanguri Road including conversion of STP bridge to Rcc bridges(BTC Package) 07/02/2005 2049.16 2049.15 1947.00 95 % 28/02/2009
142. Improvement of North Kajolgaon Bengtol Sonitpur road, Chirang(BTC Package) 07/02/2005 810.00 809.99 786.66 97 % 15/09/2008
143. Construction of Road from NH-31 at Barama to Masalpur, Baska(BTC Package) 07/02/2005 1443.00 1086.00 1173.85 108 % -
144. Improvement of Jalah Rupahi Saudarbhitha Gobardhana road, Baska(BTC Package) 07/02/2005 1000.00 1000.00 794.89 79 % -
145. Improvement of Udalguri Bhakatpara road via Bhairaguri, Udalguri(BTC Package) 07/02/2005 444.00 443.99 433.47 98 % 20/02/2007
146. Improvement of Barnagaon Pakribari road, Udalguri (BTC Package) 07/02/2005 150.00 150.00 146.38 98 % 30/09/2007
147. Improvement of Kalaigaon Kundarbil road, Udalguri (BTC Package) 07/02/2005 132.00 131.99 128.96 98 % 09/01/2009
148. Improvement of Dhamdhama Tupalia Subankhata (DTS) Road (Metalling and black-topping of remaining stretches including improvement of existing metalled surface(BTC Package) 31/12/2004 1372.00 1372.00 1331.57 97 % 05/09/2008
149. Construction of Khanda Road from Dawdhara to Doomni via Nawputa in Baska Distt.(BTC Package-2) 20/03/2012 1075.00 469.30 0.00 0 % -
150. Road improvement projects in NC Hills (6 No.) 10/03/2000 498.00 498.00 498.00 100 % 31/03/2002
151. Construction of RCC Bridge No.2/2 and 4/2 including approaches on Gurnagar Tikrikilla Road in Goalpara District 16/05/2006 355.19 252.28 111.25 44 % -
152. Goreswar to Khoirabari Road (BTC Package) 31/10/2005 657.28 657.28 638.15 97 % 30/09/2009
153. Bhergaon-Chouni-Khagrabari-Dimakuchi Road (BTC Package) 31/10/2005 131.61 131.61 131.61 100 % 20/05/2010
154. Lailongpara-Kopati Road Via Boro Bazar(BTC Package) 31/10/2005 131.05 131.04 127.23 97 % 30/09/2009
155. Khowrang Mahanpur Road (BTC Package) 31/10/2005 250.00 250.00 246.29 99 % 06/10/2008
156. Chapaguri-Khagrabari Road(BTC Package) 31/10/2005 630.00 630.00 624.69 99 % 31/12/2010
157. Tulsijhyora-Kailamaila Road via Amguri(BTC Package) 31/10/2005 900.00 900.00 887.74 99 % 31/01/2011
158. Bijni-Panbari Road(BTC Package) 31/10/2005 1558.58 1558.58 1261.88 81 % -
159. Gossaigaon to Kazigaon via Bhukka, Tipkai Road(BTC Package) 31/10/2005 1100.00 1100.00 876.78 80 % -
160. Construction of RCC Bridge No. 2/1 on Kokrajhar Monakocha Road over River Gaurang in Kokrajhar District with approaches 28/10/2005 990.63 882.74 827.74 94 % -
161. Construction of RCC Bridge No. 9/2 on Borbhogia Mikirbhata Road in Morigaon District with approaches 28/10/2005 238.96 212.93 191.94 90 % -
162. Construction of RCC Bridge No. 17/4, 19/4, 20/2 and 26/1 on Mt. Sepon Sunpura Road in Sivasagar District (Assam) with approaches 28/10/2005 377.86 336.72 336.72 100 % 06/05/2010
163. Construction of RCC Bridge No. 3/2 over River Mansiri on Charduar Road with approaches in Sonitpur District 28/10/2005 165.75 147.70 147.70 100 % 28/01/2008
164. Construction of RCC Bridge No. 4/1, 6/1 and 14/1 on North Lakhimpur Kamalabari Road 28/10/2005 455.27 405.69 179.97 44 % -
165. Construction of RCC Bridge No. 2/3, 5/1, 9/1, 11/1, 15/3, 16/1, 18/1 and 19/4 on Itakhola Pavoi Road in Sonitpur District (Assam) with approaches 28/10/2005 875.42 456.41 386.59 85 % -
166. Construction of RCC Bridge No. 1/1, 4/1, 8/1 and 9/2 on Fakiragram Sapatgram Road in Dhubri District with approaches 28/10/2005 514.51 458.48 458.48 100 % 30/12/2009
167. Construction of RCC Bridge No. 6/1 on Chariali Pavoi Road in Sonitpur District with approaches, protection work and sub-way 25/10/2005 88.53 78.90 78.90 100 % 30/03/2010
168. Construction of RCC Bridge No. 16/1, 19/1 and 19/3 on Bagals Road in Nalbari District with approaches 31/10/2005 404.73 238.93 236.59 99 % -
169. Construction of Road from Beltola Chariali to Sarusajai (Bishnu Rabha Path), Guwahati (Assam) 27/12/2005 777.31 692.66 692.66 100 % 31/01/2007
170. Improvement of Tihu Doomni Road leading to Indo-Bhutan foot hills from 7th to 25 km in Baska district(BTC Package) 27/12/2005 995.00 995.00 965.99 97 % 05/03/2009
171. Improvement of Khoirabari MPK road (Andherighat) to Harisinga via Bhergaon, Tangla and Purandia 42.25 km length with conversion of 11 SPT bridges to RCC(BTC Package) 27/12/2005 2650.26 2650.26 2209.34 83 % -
172. Construction of Kashikotra Bamungaon Bengtol Road(BTC Package) 27/12/2005 1169.00 1169.00 966.32 83 % -
173. Construction of RCC Bridge No. 1/1, 3/1, 3/2 and 4/1 on Bhairabpur to Kulibazar Road in Dhemaji District (Assam) with approaches 27/12/2005 466.44 415.63 258.93 62 % -
174. Construction of RCC Bridge No. 6/1, 7/1, 8/1, 8/2, 9/1, 11/1 and 11/2 on Sepon Suffry Road in Sivasagar District (Assam) with approaches 27/12/2005 411.17 293.24 124.59 42 % -
175. Construction of RCC Bridge No. 10/1 and approaches on Khowang Bhamun Road in Dibrugarh District of Assam 27/12/2005 103.25 92.03 43.49 47 % -
176. Construction of Additional Two Lane Rail-Over-Bridge (ROB) on A.T. Road at Maligaon, Guwahati (Assam) 27/12/2005 1355.92 1202.29 1202.29 100 % 17/10/2007
177. Construction of RCC Bridge No. 5/1 on Burhagohain Tinthengia Road in Dibrugarh District of Assam 21/12/2005 98.81 88.06 88.06 100 % -
178. Construction of RCC Bridge No. 1/1, 3/2 and 5/3 on Tupia Balijuri Road in Sonitpur District of Assam with approaches 21/12/2005 271.84 0.00 0.00 0 % -
179. Construction of RCC Bridge No. 4/1, 10/1, 11/1, 11/2, 12/1 and 13/1 on Dekapam to Somkong via Missamara Road in Dhemaji District of Assam with approaches 27/12/2005 688.10 0.00 0.00 0 % -
180. Construction of RCC Bridge No. 2/1 on Bamunbari to Jariguri Road in Dibrugarh District of Assam with approaches 21/12/2005 108.05 77.80 56.09 72 % -
181. Construction of RCC Bridge No. 5/1 on Sonakhira Bubrighat Road in Karimganj District (Assam) with approaches and protection work 03/01/2006 97.26 86.67 86.67 100 % 14/10/2009
182. Construction of RCC Bridge No. 11/1 on Teok Boloma Nakachari Road in Jorhat District (Assam) with approaches 03/01/2006 109.17 97.46 34.39 35 % -
183. Construction of RCC Bridge No. 24/2 and 32/2 on Mt. Golaghat Merapani Road in Golaghat District (Assam) with approaches and protection work 03/01/2006 185.67 165.45 165.45 100 % 19/10/2009
184. Construction of approach road leading to Industrial Growth Centre at Balipara in Sonitpur District (Assam) 27/12/2005 268.65 241.79 241.79 100 % -
185. Construction of RCC Bridge No. 10/1 on Gogamukh Ghilamara Road in Dhemaji District (Assam) with approaches 25/01/2006 108.41 74.45 74.45 100 % -
186. Construction of RCC Bridge No. 5/1 on river Bharalkunda, 7/1 on Sister-par Beel, 8/1 on Dulani Beel, 9/9 on Distributary of river Champamati and 11/1 on Hill Canal including approaches on Jogighopa Chapar Road in Bongaigaon District in Assam. 27/06/2006 709.41 632.16 632.16 100 % 30/06/2010
187. Construction of RCC Bridge No. 2/3 on river Bhulla, 3/2 on river Lakhi and 7/2 on river Lakhimorasuti on Bengbari Ambagaon Road in Udalguri District, Assam 27/06/2006 632.85 563.93 563.93 100 % 08/01/2010
188. Construction of RCC Bridge No. 2/4, 6/1 and 8/1 on river Kaldia including approaches on Dr. Jina Ram Das Road in Barpeta District (Assam) 27/06/2006 535.85 385.82 296.26 77 % -
189. Improvement of Nagaon Morikolong Nanoi dakhinpath Road under Nagaon district 26/11/2007 199.03 177.35 177.35 100 % 16/02/2010
190. Project for Road Network of Jorhat Master Plan Area in Jorhat District 12/09/2006 461.00 402.84 391.60 97 % -
191. Improvement of Barpeta Bashibari Road leading to Manas Sanctuary from km. 1st to Km. 21st in Barpeta District in Assam 31/12/2006 1235.65 1098.63 995.52 91 % -
192. Improvement of Roads and Natural Drainage System within Greater Tezpur Town 28/03/2007 2551.78 348.13 279.35 80 % -
193. construction of RCC Br. No. 4/1 & 6/1 with approaches on J.B road in Jorhat distt. 21/06/2007 324.40 289.07 193.12 67 % -
194. construction of road and minor bridge from Motinagar to Buban hill Temple - Phase I 24/10/2007 326.07 233.87 102.71 44 % -
195. Improvement of Dalgaon Kopti Road (Orang - Dalgaon Road) 26/10/2007 235.71 106.26 50.48 48 % -
196. Improvement and widening of Bishmuri Saralpara Sarbhanga Road (BTC Package -2) 20/03/2012 2679.00 1169.00 0.00 0 % -
197. Upgradation of Dalgaon Town to Sialmari via Dekerigaon 24/10/2007 251.73 113.82 101.65 89 % -
198. Improvement of Nagaon-Barapujia Road under Nagaon Dist. 22/11/2007 298.00 265.54 265.54 100 % 01/03/2011
199. Construction / improvement of Batabari Kopati road 26/10/2007 213.72 95.40 0.00 0 % -
200. Construction of Road from Bhangarpar to Chandranathppur via babur bazar (Length 5.5 KM) 20/12/2007 249.05 179.73 79.69 44 % -
201. Improvement of roads in Jorhat Town 20/12/2007 250.00 223.95 174.38 78 % -
202. Improvement of Roads in Sivasagar Town 20/12/2007 242.46 216.05 216.05 100 % 31/12/2009
203. Widening and Raising of Nazirakhat Sonapur Road (Length 6.00 km) 20/12/2007 265.08 238.57 238.55 100 % 03/03/2011
204. Construction of Dibrugarh Sapekhati road from km 12 to Km 18 along with 2 RCC bridges No. 18/1 and 19/1 with approches (Bridge over river Buridihing at Saraighat) 19/12/2007 2116.45 1495.26 1495.26 100 % -
205. Improvement of road from Kahilipara to Don Bosco School at Guwahati in Assam 31/12/2007 252.16 226.94 226.94 100 % 30/06/2010
206. Improvement of Rampur Model Road starting from NH - 37 in Kamrup District 05/03/2008 224.58 200.13 199.99 100 % 18/05/2009
207. Construction of RCC Br. No. 1/1 over River Pota on Hazuwa Nalbari Road in Baska District in Assam 27/03/2008 264.01 190.08 83.16 44 % -
208. Construction of RCC Br. No. 1/1 over regular Channel Gadadhar on Silerpar - Borshijhora Road in dhubri District 28/03/2008 450.73 405.66 405.66 100 % 31/03/2011
209. Construction of RCC Br. No. 1/1 over Santijan on Srimanta Sankardev Govesona Kendra Road in Nagaon Road 28/03/2008 280.55 249.99 138.37 55 % -
210. construction of RCC Br. No. 4/1 on Belguri - Satrasal Road in Dhrubri District 27/03/2008 273.31 245.98 245.98 100 % 05/04/2011
211. Metalling and Black Topping of Swapanpur to Ramchandi Road of Hailakandi District. 27/03/2008 379.75 273.12 119.62 44 % -
212. Construction of 4 lane Tripura road including electrical works from NH - 37 to GS Road 28/03/2008 1136.50 1022.85 1022.85 100 % 30/04/2010
213. Construction of RCC bridge at 7th Km of Kathal Road over river Ghagra including approaches and protection work in Cachar District. 28/03/2008 250.00 178.75 78.75 44 % -
214. Construction of RCC bridge no. 10/1 & 18/1 on Bagals Road in Nalbari District with approaches 30/09/2008 308.11 219.55 205.92 94 % -
215. Construction of RCC bridge no. 18/2 over stream Bahanigaon & bridge no. 19/1 over river Kachikata on Laluk-Narayanpur via Bihpuria Road in Lakhimpur District 30/09/2008 208.70 149.98 65.68 44 % -
216. Construction of RCC bridge No. 4/1, 7/1, 8/1 and 11/1 over field canal / River Sakati on Abhyapuri Tilungia Road with approaches and protection works in Bongaigaon District 07/11/2008 338.09 105.42 100.00 95 % -
217. Construction of RCC Bridge no. 5/3 on Bhorbhogia Mikirbheta Dhing Road with approaches in Morigaon District 25/11/2008 241.17 214.90 171.91 80 % -
218. Metalling and Blacktopping of Gunjung Maibang Road from 17th to 28.78 KM(NC Hills) 18/08/2009 640.80 198.71 0.00 0 % -
219. Construction of RCC bridge No. 57/1 on Gaurisagar Moran Road and construction of RCC bridge no. 15/2 over River Disam on Naharkatia - Tinkhong Road under Dibrugarh Rural Road Division 10/12/2008 406.12 289.52 116.77 40 % -
220. Conversion of SPT Bridge 20/1 over River Gangia into RCC Bridge on Gosaigaon Sapatgram Road in Kokrajhar District(BTC Package) 28/11/2008 1082.68 541.34 200.00 37 % -
221. Construction of RCC Br. No. 32/1 on AT road (old) including approaches with protection works in Goalpara 30/03/2009 739.12 230.51 166.33 72 % -
222. Constn. of Br.No. 28/1 on Dehangi Dayangmukh Road over thaijuwari Nala & Langlodisa Nala (PWD Roads Haflong Division)(NC Hills) 30/03/2009 355.00 111.76 0.00 0 % -
223. Construction of RCC Br. No. 7/1 on Dharamtul Dandua Road with approaches 30/03/2009 248.42 177.08 104.42 59 % -
224. Improvement of Badlapara to Dharamjuli Road under Udalguri Rural Road division 31/03/2009 403.35 355.90 355.90 100 % 20/09/2010
225. Constn. of RCC Br. No. 22/1 over river Diffoloo on Chowkihola Panjan Deithor Malasi Dirring Kohora (CPDMDK) Road with approaches and protection works(Karbi Anglong) 30/03/2009 303.82 94.87 0.00 0 % -
226. Improvement of BBDC Road at 31 Km (Karbi Anglong) 16/06/2009 4017.23 1216.93 0.00 0 % -
227. Construction of RCC Bridge No. 8/6 over river Dirring, (b) Bridge No. 18/1 over river Borjan, (c) Bridge No. 19/1 over River Borjan,(d) Bridge No. 23/3 over River Donjon, (e) Bridge No. 27/3 Over River Kokosang (2) Br. No. 2/1 ovr river Kohra (KarbiAnglon 14/07/2009 1138.37 351.19 0.00 0 % -
228. Construction of RCC Bridge No. 2/1 on Nandini Karaimari Road in Assam 14/07/2009 658.13 204.25 0.00 0 % -
229. Construction of RCC Bridge No. 4/1 on Garmari Gagalmari Road 14/07/2009 233.44 168.02 72.81 43 % -
230. Rupshir Ali (Construction of Bridge Nos. 3/2,5/2 &5/4) 14/07/2009 210.00 151.20 66.00 44 % -
231. Construction of RCC Bridge No. 7/1,15/1 and 19/1 on Nagaon Barapujia Road(NH-38) Road division 18/08/2009 465.83 146.00 0.00 0 % -
232. Construction of RCC Bridge No. 12/1 on Goroimari -Dewaguri Laharighat Road with approaches in assam 30/09/2009 317.34 113.11 0.00 0 % -
233. Improvement and upgradation of Chencoories Elgin Road including construction of Major RCC bridge over river Ghagra 15/10/2009 1180.91 416.60 58.17 14 % -
234. Improvement of Municipal Roads in Narayanpur Town in Assam 20/01/2010 400.00 141.17 0.00 0 % -
235. Construction of RCC Br. No. 5/1 on Jajari - Chabukdhara Road over River Sonai under Nagaon Rural Road Division 03/02/2010 236.38 168.93 85.52 51 % -
236. Construction of RCC Br. No. 6/1, 9/1 & 10/1 on Ambagaon Kathpara Solmari Singiari Road (NG-M-17) in Nagaon District 03/02/2010 239.02 85.52 71.68 84 % -
237. Construction of RCC Br. No. 8/1 on Bhalukmari in Mikirbheta Bhurbandha Road with approaches and protection work in Morigaon District 03/02/2010 254.62 181.51 90.76 50 % -
238. Improvement of Tangla Bhergaon Ramgaon Road from Ch.00 M to 9400 M including cross drainage works in Udalguri 05/02/2010 1043.34 736.45 366.37 50 % -
239. Metalling and Blacktopping of Road from Dr. Fakaruddin Ali Ahmed Path To Doulgobindapur via Nalbari Hindu Smashan, Nalbari along with Pucca Drain and RCC Slab culverts 05/02/2010 227.85 81.21 0.00 0 % -
240. Upgradation of Nagaon - Bhuragaon Road via Dhing (SH-10) under Nagaon State Road Division (Nagaon District) 22/03/2010 1151.91 410.71 410.71 100 % -
241. Improvement of Road Network leading towards Dibru- Chaikhowa National Park under Dibrugarh Rural Road division 22/03/2010 747.42 268.79 258.92 96 % -
242. Improvement of Charigaon Road under Jorhat Road Division 22/03/2010 556.98 199.82 0.00 0 % -
243. Construction of RCC Bridge No. 4/1 on Dimou-Raidongia Road over river Sonai under Nagaon Rural Road Division (Nagaon District) 05/04/2010 270.98 96.50 0.00 0 % -
244. Metalling and Blacktopping of Road from Borhapjan samdang via Nahoroni road to Sukanguri L.P School in Tinsukia Rural Road Subdivision / Division 15/09/2010 321.45 229.15 114.15 50 % -
245. Construction of RCC Bridge No. 3/1 on Majgaon Shantipur Road over River Sonai under Nagaon rural road Division 17/06/2010 333.19 118.76 0.00 0 % -
246. Improvement of Jalah to Kumarikata including 2 Nos. of Bridges over River Kaldia and Diring in Baska District(BTC Package) 08/10/2010 2121.20 1060.60 273.00 26 % -
247. Metalling & Black Topping of Road from Circuit House Tinsukia to NH-37 via Okanimuria Borguri Okanimuria Nakhrai and Lunpuria Kaibortogaon in Tinsukia Rural Road Subdivision/ Division 29/10/2010 524.10 185.75 0.00 0 % -
248. Construction of Moran Netai Road, Dibrugarh 10/11/2010 303.42 107.49 0.00 0 % -
249. Construction of road from Hidipi to Lahorijan - goutom Basti road in Karbi anglong 10/11/2010 485.41 170.76 0.00 0 % -
250. Construction of Tiphuk Jajolipukhuri Road with RCC Bridge No. 3/3 in Sibsagar District 10/11/2010 559.91 199.64 0.00 0 % -
251. Construction of Bridge No. 1/2 & Bridge No. 4/1 on old AT Road under Dibrugarh Rural Road Division in Dibrugarh Distt. 10/11/2010 290.37 208.80 103.49 50 % -
252. Construction of RCC Bridge over River Aie 10/11/2010 7883.65 5620.01 2509.96 45 % -
253. Construction of Mohmora Ali with RCC Bridge No. 9/2 in Sibsagar District 12/11/2010 771.96 271.80 0.00 0 % -
254. Improvement of Tangla Kachubil Road (BTC area) 15/11/2010 1079.86 384.90 196.03 51 % -
255. Construction of RCC Br. No. 2/2 and 2/3 (Renamed as Br. Nos. 3/1 and 4/6) on Shyamaprasadpur to Dossgram Road via Swapnargul over stream Singrai in Cachar District 29/11/2010 257.00 91.61 0.00 0 % -
256. Const of RCC Br. No. ½ Over river Aie at Chillapara Kahibari villages on the road from Kokoijana 31-National High way to Nagaon.Manikpur 31 National Highway via Kirtanpara, Numbarpara villages under Bongaigaon rural road Divn. 29/11/2010 4001.26 1425.60 0.00 0 % -
257. construction of RCC Bridge No. 8/1 over Gurufella river on Gossaigaon - Sapatgram Road)(BTC Package-2) 14/12/2010 792.00 396.00 0.00 0 % -
258. Construction of RCC Bridge No. 6/3 over Gongia river on Dotoma - Bhawraguri Road)(BTC Package-2) 14/12/2010 800.00 400.00 0.00 0 % -
259. Construction of RCC Bridge No. 3/1 over Puthimari river at Dolonghat (Dhulabari))(BTC Package-2) 14/12/2010 800.00 400.00 0.00 0 % -
260. Improvement of Mahilapara Dongapara Barangajuli PWD Road. 14/12/2010 835.19 297.69 0.00 0 % -
261. Construction of Zoo Japorigog Road (CH.0.00 to 1865.00 m from R.G. Baruah Road near State Zoo to Junction Point of Dispur Narengi Road including electrical works 13/12/2010 619.86 223.13 0.00 0 % -
262. Improvement of Road Network at Sonari Town under Charaideo Rural Road Division 13/12/2010 723.74 260.55 0.00 0 % -
263. Construction of RCC Br. (a) No. 1/1 and 2/1 on Deroi Rongoli road (b) No. 2/1 on Deopling Ramuagar road and No. 3/1 ghilaguri Road 13/12/2010 391.18 138.06 0.00 0 % -
264. Construction of RCC Bridge No. 24/1 on Morigaon Moirabari Road in Morigaon District 25/01/2011 315.54 111.92 0.00 0 % -
265. Constyruction of RCC bridge no. 13/1, 13/2 and 30/2 on Mohbondha Road 25/01/2011 614.33 219.15 0.00 0 % -
266. Construction of Br. no 2/1&4/1 on Raha Barapujia road over river Botamari and Hatibandha with approaches in Nagoan District 22/02/2011 369.00 130.69 0.00 0 % -
267. Improvement of Roads in Biswanath Chariali Town 22/02/2011 1174.43 414.35 0.00 0 % -
268. Improvement of Bezera Balikuchi road 22/02/2011 370.65 132.20 0.00 0 % -
269. Improvement of JB Road 26/05/2011 297.37 105.82 0.00 0 % -
270. upgradation of NT road through Ramphalbil Bazar to all weather road with conversion of SPT bridges into RCC bridge(International Border Areas) 27/06/2011 764.18 269.71 0.00 0 % -
271. Construction of RCC Br. No. 1/1 over River Kalang on Ghahi - Borjhora Road under Nagaon Rural Road Division (Nagaon District) 27/06/2011 281.12 100.22 0.00 0 % -
272. Improvement of Chintagaon Botiamari Road in Udalguri District 15/09/2011 898.26 321.72 0.00 0 % -
273. Construction of Road with MTBT from UT Road at Dimakuchi Donbosco School to Badlapara via Kalikhola Road, Udalguri in Assam 14/12/2011 620.91 223.17 0.00 0 % -
274. Upgradation of Road from NH-31 (C) via Serfanguri, Nepalpara, Athiabari, Ebargaon, Thaigiriguri and No. 2 Hazarikapara to Kapuragaon 14/12/2011 759.70 269.79 0.00 0 % -
275. Construction of RCC Br. No. 8/1 over Saral Bhanga on Dotma Balajan Road 19/12/2011 1202.31 428.55 0.00 0 % -
276. Construction of 4 Nos. road including box culverts and pucca drainage in Lakhipur Town 29/12/2011 1424.77 509.58 0.00 0 % -
277. Construction of Flyover at the Intersection of Pramathesh Barua Road and N.F Railway Track at Bijni Town in Assam 29/12/2011 1963.35 706.55 0.00 0 % -
278. Improvement of Rongkhang Basti to Thekerajan Road (KAADC) 29/12/2011 1418.14 504.90 0.00 0 % -
279. construction of road from rangamati to kalaigaon road janaram chowka to aaola chowka 31/01/2012 575.35 202.77 0.00 0 % -
280. Improvement of road from Bashbari to Gossaigaon via Dingdinga, Kokrajhar District (D.K. Road)(BTC Package-2) 20/03/2012 2500.00 1091.00 0.00 0 % -
281. Met. And Blacktopping raod from Lalmati to Manglajhora in Kokrajhar District.(BTC Package -2) 20/03/2012 600.00 261.83 0.00 0 % -
Total for Assam (215 Projects) 135954.20 90004.52 62009.50    
Manipur
282. Construction of Bally Suspension Bridge (360 ft. span) over Barak River on Tamenglong - Tousem - Haflong Road 26/12/2005 338.78 296.59 259.00 87 % -
283. Construction of Keishmathong Bridge 17/02/2006 347.00 302.90 246.04 81 % 16/11/2009
284. Construction of Lamlong Bridge 17/02/2006 454.00 397.01 397.01 100 % 18/07/2009
285. Construction of Singjamei bridge 29/10/2004 369.00 335.47 335.47 100 % 16/11/2009
286. Senapati-Phaibung Road (128.90 Kms.) 31/03/2000 10517.70 9423.00 7959.19 84 % -
287. Construction of Bridge over Thoubal River at Leishangthem 30/11/2006 340.70 297.70 297.70 100 % 03/06/2010
288. Construction of Kumbi Bridge over Khuga River at km 10.75 of Moirang-Kumbi Road 04/01/2007 432.00 377.40 361.70 96 % -
289. Construction of Bridge at Irong Ichin 30/11/2006 334.21 292.03 233.28 80 % -
290. Construction of Bridge over Imphal River at Kiyamgei Mang Mapa 30/11/2006 471.22 411.74 411.74 100 % 21/02/2012
291. Construction of Bridge at Babu Bazar 30/11/2006 292.66 255.72 255.72 100 % 16/07/2011
292. Construction of Bridge over thoubal River at Haokha 30/11/2006 275.60 240.82 240.89 100 % 16/07/2011
293. Construction of Brodge over Heirok river at Heirok Chingdongpok 25/05/2007 220.45 192.63 192.63 100 % 30/06/2010
294. Improvement of Jiri - Tipaimukh Road (8-48 Km) 31/12/2007 1856.33 1637.95 1228.35 75 % -
295. Improvement of Lamsong-Khonghampat Road 07/03/2008 268.34 236.78 236.78 100 % 16/07/2011
296. Improvement of Sawombung-Sagolmand Road from 0-12 Km 03/06/2009 222.76 103.68 70.16 68 % -
297. Construction of bridge over Jaduiki river on Tamei Kuilong Road 30/09/2009 226.48 79.00 0.00 0 % -
298. Construction of bridge over Layii river on Kharasom Lazo to Layii Road 30/09/2009 353.21 124.65 0.00 0 % -
299. Construction of RCC bridge over Iril River at Keiro Litan Makhong in Manipur 13/04/2010 625.19 220.65 0.00 0 % -
300. Construction of RCC bridge (60 m) over Thoubal River at Thoubal Mathak Leikai Keirambi in Manipur 13/04/2010 505.73 178.45 178.45 100 % -
301. Construction of RCC bridge over Imphal river at Mongkhang Lambi 24/06/2010 579.04 204.35 0.00 0 % -
302. Construction of Road from Aibulon to Bungpilon in Churachandpur 15/03/2011 1118.86 402.75 0.00 0 % -
303. Construction of RCC Bridge over Imphal river at Moirangkhom (Old Thumbuthong) in Imphal West, Manipur 28/06/2011 713.20 256.75 0.00 0 % -
304. Construction of RCC bridge over Iril river at Chingaren Mapa in Imphal East, Manipur 28/06/2011 637.12 229.30 0.00 0 % -
305. Construction of bridge over Challow river between Chingai (Kuingai) and Tusom in Manipur 28/06/2011 302.38 108.85 0.00 0 % -
Total for Manipur (24 Projects) 21801.96 16606.17 12904.11    
Meghalaya
306. Providing passing places in portion from 0 to 9-th Km. Of Smit- Mawkynrew- Mawlat Road etc. 11/07/2001 493.00 493.00 493.00 100 % 21/05/2004
307. Strengthening including widening of existing pavement into Intermediate Lane of 4.75 m. width of Mawshynrut- Nongchau Rd. 11/07/2001 732.61 732.61 732.61 100 % 14/02/2006
308. Strengthening of Baghmara-Maheshkhola Road (Strengthening of weak pavement from 35th Km. To 74th Km. In diff. Kms-15). 11/07/2001 186.00 186.00 186.00 100 % 21/05/2004
309. Widening and Strengthening of hard crust on Mawngap-Mairang Road (5th to 24th Km.) 11/07/2001 452.00 452.00 452.00 100 % 21/05/2004
310. Reconstruction of Bridges and Approaches on Mawphlang - Balat Road 18/10/2005 900.53 786.86 786.86 100 % -
311. Upgradation of Double Lane and Strengthening of Dkhiah - Sutnga - Saipung - Moulsei - Haflong Road (9th to 16th km) 18/10/2005 445.88 389.60 389.60 100 % 28/06/2011
312. Construction of RCC Bridge over River Daru on Ampati-Purkashia Road (2nd km) to Ampati Village 23/12/2005 506.80 342.61 273.44 80 % -
313. Improvement, Widening, Strengthening including Reconstruction of Bridges and Culverts of Rymbai - Iapmala - Suchen Road (1-17 Km) 28/12/2005 1877.49 1640.53 1640.53 100 % -
314. Improvement, widening including metalling and blacktopping of Dkhiah - Sutnga - Saipung - Mouslei - Halflong Road (16 Km) 26/03/2007 722.08 630.94 630.94 100 % -
315. Construction and Strengthening of Jakrem - Ranikor Road ( 6-15 Km) 13/07/2007 416.40 331.59 292.00 88 % -
316. Construction including metalling and black topping of Lumshnong - Umlong Road (0-8 km) 26/09/2007 601.76 531.00 531.00 100 % -
317. Improvement including metalling and blacktopping of Mawkyrwat - Rangblang Road (12th to 19th Km) (8 Km) 27/09/2007 480.00 417.00 417.00 100 % -
318. Widening of road to double lane from Araimile to Dakopgre of Tura town (4 Km) 27/09/2007 313.83 276.91 276.91 100 % -
319. Reconstruction of bridge over river Leiten (Bridge No-31/1) on Dkhiah-Sutnga-Saipung-Mawblei-Halflong Road 27/09/2007 243.15 214.54 214.54 100 % 28/06/2011
320. Improvement, Widening, Strengthening including Metalling & Blacktopping of a road from 9th Mile of NH-37 (Guwahati - Shillong road) to Killing – Pilangkata (6.00KM) 28/09/2007 312.73 275.94 275.94 100 % -
321. Improvement including metalling and blacktopping of Mukhaialong Lumshyrmit Road (19 km) 16/11/2007 911.00 803.83 803.83 100 % -
322. Construction including metalling and blacktopping of a Road from Mushut to Lumputhoi via Rngad (12 Km) 26/12/2007 487.21 429.89 429.89 100 % -
323. Upgradation and Strengthening of Garobadha - Betasing Raod via Rangasakhona (from 6th Km of GR road upto 6th Km of BM road via Khasibil) in Tura District (7.833 Km) 31/12/2007 1137.56 1003.72 1003.72 100 % -
324. Improvement, Metalling & Blacktopping of a road from NH-51 to Rongsigre (4.725 Km) 31/12/2007 327.08 288.68 288.68 100 % -
325. Widening of roads into double lane in Williamnagar town (8 Km) 28/03/2008 1512.67 1334.71 1072.91 80 % -
326. Construction of remaining portion of Mawsahew- Nongsteng-Umblai-Mawphu Road (6th to 13th Km) 30/09/2008 953.88 300.47 229.50 76 % -
327. Improvement including Metalling & Blacktopping of road from Sonapur (NH-44) to Lad Borsora (10 Km) 10/10/2008 832.99 734.99 420.69 57 % -
328. Improvement/construction including Metalling and Blacktopping of a double lane road from Rymbai to Deichynrum (7Km) 20/02/2009 602.56 531.67 425.93 80 % -
329. Rehabilitation of Lyngkhat - Dawki Road (9.75 km) 30/09/2009 1160.85 1024.29 466.57 46 % -
330. Reconstruction of Bridges and Approaches on Damalgre - Mellim – Boldamgiri road, Tura (Bridge No.5/3, 8/5, 9/1 and 10/2) 30/09/2009 1146.94 412.90 195.00 47 % -
331. Reconstruction of bridges on Kherapara to Dekubazar (Br.No.2/5, 5/3 & 10/2) 02/02/2010 852.89 307.00 188.50 61 % -
332. Construction of road from Rongjeng-Mangsang-Adorgre road including metalling and blacktopping (33rd to 38th Km) with bridges (5.16 Km) 25/03/2010 439.24 158.13 74.79 47 % -
333. Widening to double lane standard including M&BT of Dkhiah-Sutanga-Saipung-Moulsei-Halflong Road (portion 1st to 8th and 18th Km), Jaintia Hills District, Meghalaya 09/11/2010 1577.50 567.90 175.89 31 % -
334. Improvement, widening, strengthening including Metalling and Blacktopping of a road 9th Mile NH-37 Guwahati-Shillong road to Killing Pillankata (7th to21.50km) in Meghalaya 23/12/2010 1096.17 394.62 0.00 0 % -
335. Re-Construction of SPT bridge No. 14/1 over Umngi River to Permanent RCC Bridge at 14th km of Laitmawsiang-Mawthawpdah road including approaches - West Khasi Hills Distt. in Meghalaya 23/12/2010 706.61 254.38 58.00 23 % -
336. Construction including metalling and Blacktopping of Bandapara-Mallangkona of Shallang road (52 KM) phase- I 10.00 Km- West Garo Hills Distt. in Meghalaya 08/07/2011 1072.09 385.95 0.00 0 % -
337. Construction including M & BT of a road from G. S. Road NH 40 to Nongthymmai, Umsning (4.311 Km), Ri-Bhoi Distt. in Meghalaya 16/09/2011 426.15 153.41 0.00 0 % -
338. Widening & Strengthening of Damara-Mendipathar-Songsak-Williamnagar Road (Conversion of SPT bridges to RCC bridges) 02/01/2012 594.83 214.00 0.00 0 % -
339. Strengthening improvement including metalling & blacktopping of road from Bholaganj to Nongiri, including construction of a major bridge at Tharia over river Wahrew 02/01/2012 2936.89 1057.28 0.00 0 % -
340. Construction of RCC bridges No. 3/1, 7/1, 7/2 and 8/1 on Ampati - Mankchar Road 15/02/2012 500.04 180.02 0.00 0 % -
341. Construction length of possengagre to Anangpara including Metalling and Blacktopping upto Anchenggre 12/03/2012 688.94 248.02 0.00 0 % -
Total for Meghalaya (36 Projects) 28648.35 18486.99 13426.27    
Mizoram
342. Improvement and widening of Bawngkawn to Durtland Road 21/03/2003 681.00 681.00 681.00 100 % 29/05/2004
343. Bridge over River Chawngte(P to C)(LAI&Chakma ADC) 07/01/2004 255.53 243.79 243.79 100 % 14/01/2008
344. Bridge over River Chawngtelui on Diltlang to Chawngte Road(LAI ADC) 07/01/2004 203.49 194.00 194.00 100 % 15/11/2006
345. Bridge over River Tuisih on Tuipang-Zwangling-Chheihhlu Road(Mara ADC) 07/01/2004 114.06 108.70 108.70 100 % 28/04/2007
346. Bridge over River Vanva on Haulawng-Bualpui-Chhiphir Road 07/01/2004 145.67 138.72 138.72 100 % 15/05/2007
347. Chawngte-Borapansury Road within Chakma Autonomous District Council 21/10/2003 1046.00 975.01 975.01 100 % 25/03/2010
348. Construction of Link Roads to Bamboo Plantation - Plot No. A from W.Serzawl Saiphal/Saitlaw 18 kms 29/09/2003 582.00 582.00 550.00 95 % 31/03/2009
349. Construction of Link Roads to Bamboo Plantation - Plot No. B from Dur Lui - Sairum and Dur Lui - Mualkhang 29/09/2003 616.62 616.62 616.62 100 % 29/03/2007
350. Lungtian-Mamte Road via Vartek Kai within Lai ADC 21/10/2003 2665.00 2477.45 2477.45 100 % 31/03/2010
351. Construction of 3 Bailey Bridges in Mizoram 26/09/2006 649.42 379.51 204.57 54 % -
352. Construction of Link Road to Bamboo Plantation Areas from Saiphal to Hortoki (0-27.5km) in Mizoram 24/11/2006 1299.67 818.80 409.40 50 % -
353. Construction of Bamboo Plantation Link Road to proposed Bamboo Plantation Areas from tuirial Airfield to Bukpui (0-40) 01/12/2006 2239.02 705.29 705.29 100 % -
354. Construction of Bamboo Plantation Link road from tuiral airfield to Bukpui Phase - II (40 - 84) 01/12/2006 2512.50 791.44 791.44 100 % -
355. Upgradation of Parva-I to Simenasora Road 26/09/2007 1226.40 1082.11 755.81 70 % -
356. Construction of Bridge over Tuichang on Keituam - Artahkawn road in Mizoram 30/04/2008 259.49 81.00 81.00 100 % -
357. Construction of Longpuighat – Kukurduleya Road 03/02/2009 1152.45 689.38 344.69 50 % -
358. Road formation and restoration works at Lawngtlai Slided loctaion 18/02/2009 223.70 148.03 69.08 47 % -
359. Construction of Approach Road to Tuival from Mimbung and approach road to Godown at Kawlkulh, Mizoram 24/06/2011 367.09 129.56 0.00 0 % -
360. Construction of Sihpui to Thuampui Road in Mizoram 13/12/2010 248.23 87.61 0.00 0 % -
361. Construction of Road from Ramthar 'N' to Ramhlum Sport Complex in Mizoram 23/12/2010 202.23 71.38 0.00 0 % -
362. Construction of Road from Chuhvel to Sihthiang in Mizoram 23/02/2011 223.53 78.89 0.00 0 % -
363. Construction of Khanpui to Tualbung road 04/07/2011 197.21 69.60 0.00 0 % -
364. Construction of Jeepable Suspension Bridge over R. Chhimtuipui at Darzokai on Hnahthial to Sangau Road 02/03/2012 216.21 76.31 0.00 0 % -
Total for Mizoram (23 Projects) 17326.52 11226.20 9346.57    
Nagaland
365. Upgradation of Dimapur Khopanala Jalukie Peren Road 21/02/2006 3673.00 3305.95 3305.95 100 % 25/02/2010
366. Construction and Upgradation of road from Old Phek via Khuza to Satakha Road 22/02/2006 2917.21 2549.02 2549.02 100 % 31/03/2010
367. Improvement and Upgradation of road from Longkhum via Mangmetong - Aliba 22/02/2006 1781.00 1555.89 1555.89 100 % 09/06/2010
368. Mokokchung-Dikhu-Chare road in Tuensang Dist. (Tuensang Seminar Road) 28/02/2001 870.00 853.70 853.70 100 % 10/08/2007
369. Aboi-Tohok, 14 KM 23/10/2001 653.00 653.00 653.00 100 % -
370. Kiphire - Pungro Road (Tuensang Seminar Road) 01/04/2001 2900.00 2857.00 2856.01 100 % -
371. Mon-Namotola Road (Mon Seminar Road) 01/10/2001 958.00 958.00 950.10 99 % -
372. Tang-Junction to Chenmoho Road (Mon Seminar Road) 01/04/2001 1554.00 1489.96 1512.66 102 % -
373. Tohok-Chenkhao-Wangti,31KM 23/10/2001 818.89 797.00 790.94 99 % -
374. Dimapur to Ganeshnagar Road 30/01/2003 1212.00 1111.32 1111.32 100 % 09/06/2010
375. Khipire-Amahator-Lukhani Road (Tuensang Seminar Road) 30/01/2003 1952.40 1728.92 1409.51 82 % -
376. Lampong Singha to Phomehing via Changnyu EAC HQ. (Mon Seminar Road) 30/01/2003 878.00 0.00 0.00 0 % -
377. Replacement of Hamilton Bridge on Diku-Chare Road 21/03/2003 160.00 40.00 6.00 15 % -
378. Tohok-Chen HQ-Chenlaiso-Wangti,49 KM 12/01/2004 1111.08 998.07 971.46 97 % -
379. Construction of Road from Purana Bazar (NH-39 Bypass) to Kohima-Bokajan Road 20/09/2004 2117.63 1925.33 1924.96 100 % 29/09/2006
380. Improvement and upgradation of District Capital Roads 29/07/2004 2000.00 1817.63 1817.63 100 % 30/09/2005
381. Chantongya - Longleng Road (23 KMs) 01/03/2000 423.00 423.00 423.00 100 % 30/09/2002
382. Construction of Road to Dimapur Dist. Headquarters at Chumukedima 01/03/2000 265.00 265.00 265.00 100 % 14/08/2003
383. Improvement of Dimapur Niuland Road 01/03/2000 736.00 736.00 736.00 100 % 31/03/2003
384. Railway Over bridge at Dimapur 01/01/2001 350.00 350.00 350.00 100 % 30/09/2002
385. Improvement of Roads in Mon District (Under PM's Package) 29/09/2005 2374.78 1567.34 712.43 45 % -
386. Improvement of Roads in Tuensang District (Under PM's Package) 29/09/2005 4072.11 3282.22 3281.82 100 % -
387. Improvement of Roads in Wokha District (Under PM's Package) 29/09/2005 435.42 380.12 380.12 100 % -
388. Construction of 2 lane RCC Bridge over Dhansiri river 28/06/2007 645.19 580.67 580.67 100 % -
389. Improvement of road from Hezidesa Village to Intanki River Bridge (6.60 km) and upgradation of Road from Mounglumuk to Jalukie Zandi Village (6.30km) in Nagaland 26/09/2007 727.00 654.34 654.34 100 % -
390. Upgradation of Road from Rusoma to Kijumetuma (36.00 Km) 31/12/2007 2184.57 1966.05 1966.05 100 % 14/05/2010
391. Construction of Road from Phek to Chozuba (44.36 Km) 31/12/2007 1747.13 1450.00 1450.00 100 % -
392. Construction of Link Roads to Mineral Deposit Areas in Nagaland 16/05/2008 2653.91 2341.71 2341.71 100 % -
393. Construction of road from Razeba to Chizami via Thetsumi 18/12/2008 2572.67 2315.40 1736.08 75 % -
394. Construction of road from Ruzhazo to Phek town via Khumvophu 18/12/2008 860.04 764.86 580.05 76 % -
395. Constructon of T.Beam Girder Double Lane Bridge of IRC Class 'A' loading over river DZU-U on Rusoma to Kijumetuma road 18/12/2008 544.41 489.97 489.97 100 % 14/05/2010
396. Upgradation and Improvement of roads from Tourist Villages from major/minor hubs in Nagaland 02/03/2009 489.64 432.30 324.29 75 % -
397. Construction of road from Tamlu Administrative Hq. to Shemnyuching in Nagaland 02/03/2009 1142.95 771.46 771.46 100 % -
398. Construction & Improvement of road from Zhekiye to Hokiye via Satoi (Zhekiye to Chokhuvi)-26 km in Nagaland 02/03/2009 1693.61 1120.44 1120.44 100 % -
399. Construction of road from NH-150 to Thiphuzu (25 km) in Nagaland 02/03/2009 1192.46 1073.21 804.24 75 % -
400. Construction of road from Kephore to Kituskir (10 km) in Nagaland 02/03/2009 749.05 465.56 465.56 100 % -
401. Construction of road from Agunato-Samator Road in Nagaland 27/03/2009 1597.30 1409.80 1057.45 75 % -
402. Construction of road from Noklak to Thonoknyu via Sanglao in Nagaland 27/03/2009 844.81 760.32 569.78 75 % -
403. Construction / Improvement of road from Tuophema to Kasha (8.5 km) in Nagaland 26/03/2009 586.82 517.79 388.31 75 % -
404. Construction of Road Kohima Laike Road junction to old Puilwa -15km in Nagaland 04/09/2009 748.93 660.83 660.83 100 % -
405. Construction of Road from Yangli to Surohoto (17Km) in Nagaland 04/09/2009 894.68 789.42 789.42 100 % 10/03/2011
406. Construction of road from Longtho to Governor's Camp at Liphayan 20 km in Nagaland 30/09/2009 1094.56 965.79 772.64 80 % -
407. Construction of road from Chuchuyimlang to Mongdikang 20 km in Nagaland 14/10/2009 1106.38 976.22 823.87 84 % -
408. Improvement and Upgradation of road from NH-61 (Alichen to Mangmetong - 11 Km) to Doyang Hydro Project Phase -I in Nagaland 05/02/2010 704.14 621.29 501.29 81 % -
409. Upgradation of Dimapur-Nuiland Road from ODR to MDR (28 Kms) in Nagaland 16/08/2010 2941.08 2595.07 2076.06 80 % -
410. Upgradation of Co-Co Doyang Road (NH-61) to Kitsaki via Atoizu SDO HQ-37 (MDR) 23/12/2010 1661.12 1196.00 1196.00 100 % -
411. Improvement of road from Zhekiye to Satoi - 70 km (Ghukhuyi upto Satoi Administrative Hq., MDR-21 km) 10/11/2010 1438.84 1015.00 507.50 50 % -
412. Construction of Tizu Bridge & Chizuti Bridge at Nimi-Laluri Road to Mineral Deposit Areas 23/12/2010 2053.93 1431.59 716.00 50 % -
413. Construction of road from Kohima to Leikie road junction to Tepuiki to Barak - 10 km (MDR) 28/02/2011 968.54 348.43 0.00 0 % -
414. Construction of road from Chozuba Border Road to Kijumetuma Junction via Khusami (26 km) 15/03/2011 3435.50 1232.01 0.00 0 % -
415. Construction of road from Diezephe to Razephe via Vidima - 15 km 19/05/2011 1371.24 489.02 0.00 0 % -
416. Improvement & Upgradation of road from Border road to Changlanshu - 19 km 27/06/2011 610.78 219.13 0.00 0 % -
417. Construction of RCC T Beam girder double-lane bridge over river Tezu on Lanye to Meluri, Phek Dist 27/06/2011 900.26 323.73 0.00 0 % -
418. Construction of road from Zero Point Sanis to Woruku village - 27km (ODR) 19/09/2011 2299.44 820.96 0.00 0 % -
419. Construction of road from Pughoboto to Satakha, Zunheboto road, Zunheboto District (50km) 19/09/2011 3924.04 1411.53 1411.53 100 % -
420. Construction of road from Tuophema to Pughoboto via Kasha (Kasha to Pughoboto) - 12.47km 19/09/2011 1494.87 537.00 0.00 0 % -
421. Construction of road from NH-150 to Chokriba via Thipuzu (10 km) in Phek District 19/12/2011 1167.91 410.10 0.00 0 % -
Total for Nagaland (57 Projects) 83260.32 62801.47 53172.06    
Sikkim
422. Construction of Rural suspension Foot Bridges (35 No.) 28/02/2002 890.00 883.90 883.90 100 % 02/05/2006
423. Surface improvement/widening,carpeting and bridge replacement on Gyalshing-Soreng Road (up to Dentam): (a) Pelling - Dentam Road (20 km) and (b) Replacement of BB Lal Suspension Brdg over Kalez Khola 22/03/2004 1251.00 1099.05 1099.05 100 % -
424. Carpeting / Surface Improvement of Dentam - Uttarey Road (10 Km) in West Sikkim 30/07/2004 399.00 361.17 333.99 92 % 30/04/2011
425. Carpeting / Surface Improvement of Soreng-Budang Road via Malbassey (10Km) in South Sikkim 30/07/2004 339.00 317.12 317.12 100 % 31/03/2008
426. Carpeting / Surface Improvement, Protective works and Drainage on Namchi-Rabongla Road (26 Kms) in South Sikkim 30/07/2004 1207.00 1088.08 1088.08 100 % 30/04/2011
427. Construction of Diversion of Ranipool-Pakyong Road in East Sikkim 29/09/2004 237.00 213.27 213.27 100 % 30/04/2011
428. Replacement of 2 nos. of existing suspension bridges on Pelling-Yuksom Road in Sikkim 30/07/2004 328.00 298.88 298.88 100 % -
429. Slope stabilisation of Labing landslide (160 m) and Chongrang landslide (800 m) on Yuksom-Legship road in West Sikkim 30/07/2004 128.00 115.23 115.23 100 % 30/04/2008
430. Upgradation of Rabongla - Makha Road (26 Kms) in South Sikkim 30/07/2004 994.00 913.92 913.92 100 % 31/03/2008
431. Upgradation of Ranka Burtuk-Gangtok Road (8 kms) in East Sikkim 07/05/2004 420.00 387.20 387.20 100 % -
432. WBM Carpetting of 9 roads (9 No.) 09/03/2000 520.00 520.00 520.00 100 % 31/08/2001
433. Construction of 28 new roads (28 No.) 09/03/2000 456.00 456.00 456.00 100 % 29/05/2005
434. Strengthening of roads and bridges (8 No.) 05/02/2002 1369.00 1369.00 1369.00 100 % 22/01/2007
435. Construction of Goshkan Dara Bridge over Teesta at Singtam 15/02/2006 1338.00 1168.75 1168.75 100 % -
436. Namachi Assangthang Road under South Sikkim circle (5 km) 28/03/2008 600.00 540.00 404.52 75 % -
437. construction of pre- stressed Bridge over River Rangit on Legship Tashiding road in West Sikkim 30/09/2008 1392.45 430.40 430.40 100 % -
438. Pakyong- Machong - Rolep Road in East 04/11/2008 3338.58 1628.60 1628.60 100 % -
439. Extension of road from Chakhung Khanesherbong SPWD road to Majuwa village via Chota Samdung-3kms length alongwith 2nos. of RCC bridges in West District 18/12/2008 270.79 83.62 0.00 0 % -
440. Construction / improvement of 18.3 km road Sribadam-Deythang-Mangalbarey in West Sikkim 02/03/2009 1680.26 520.35 277.46 53 % -
441. Upgradation of LLHP to Nandok road (4kms) in East Sikkim 02/03/2009 362.77 112.95 112.95 100 % -
442. Improvement & widening of Tintek Dikchu Road - 12 km in East Sikkim 02/03/2009 1023.73 684.95 684.90 100 % -
443. Construction of link road from Passingdong P.H.E. to Linghtem Gumpha (Monastery) and Lingthem School-8km, upper Dzongo, North Sikkim 26/03/2009 765.55 516.15 516.15 100 % -
444. Construction of 70 m Span Bridge over Dev Khola along GLVC road Km 8th, South Sikkim 09/11/2010 506.34 182.28 70.00 38 % -
445. Construction of Steel Bridge at Khundrukay Khola along Yangang-Makha Road, South Sikkim 09/11/2010 241.06 86.78 86.64 100 % -
446. Construction of 40 M Span Steel Bridge over Lwang Khola along Namchi Phongla Road Km 8th, South Sikkim 09/11/2010 326.56 117.56 47.93 41 % -
447. Double laning of Sichey-Ranka Road (11 Km). East Sikkim 09/11/2010 2563.33 922.80 295.46 32 % -
Total for Sikkim (68 Projects) 22947.42 15018.01 13719.40    
Tripura
448. Widening & strengthening of Banikya Chowmuhani – Shalbagan road. (9.00 Km.) 20/03/2006 477.00 418.97 418.97 100 % 04/08/2009
449. Replacement of 2 existing semi permanent timber (SPT) bridges in Tripura on Kamalpur-Maracherra-Ambassa Road by RCC bridges 20/03/2006 428.00 373.78 227.36 61 % -
450. Replacement of 49 Timber Bridges by Belley type Steel bridge in tribal areas. 09/01/2001 2849.00 2849.00 2849.00 100 % 27/05/2004
451. Upgradation of Halahali-Ambassa-Dangabari-Bel 12/09/2001 18909.30 16284.53 14787.41 91 % -
452. Construction of RCC Bridge over river Surmacherra at Ch.30.10 Km. on Mohanpur – Simna Raod 17/08/2009 167.01 52.79 52.79 100 % -
453. Construction of RCC Bridge over river Surmacherra at Ch.34.53 on Mohanpur – Simna Raod 17/08/2009 223.74 70.29 0.00 0 % -
454. Construction of RCC Bridge over Local stream at Ch.7.00 Km on Dhanpur to Kakraban 17/08/2009 225.89 113.09 113.09 100 % -
455. Construction of RCC Bridge over Local stream at Ch.4.50 Km on Dhanpur to Kakraban 17/08/2009 177.94 157.00 157.00 100 % -
456. Construction of RCC Bridge over local stream at ch. 4.40 Km on Jogendranagar to Jampaijala Road 29/09/2009 184.08 68.10 68.10 100 % -
457. Construction of RCC Bridge over local stream at ch. 7.50 Km on Jogendranagar to Jampaijala Road 29/09/2009 255.84 90.27 0.00 0 % -
458. Construction of RCC Bridge over Kakricherra on Thalibari – Microsa 29/09/2009 209.77 151.04 75.52 50 % -
459. Construction of RCC Bridge at Ch 9.00 Km near Tulamura Market over Tulamuracherra on Gargi – Tulamura road (ODR) 14/12/2009 328.33 236.38 236.38 100 % -
460. Construction of RCC bridge over Burima river near Golaghati Market on Bishalgarh – Golaghati – Takarjala road 05/02/2010 353.19 254.28 127.14 50 % -
461. Construction of RCC Bridge over river Howrha at Ch. 0.10 Km. Champaknagar to Udaipur road (ODR) 04/02/2010 301.67 108.60 0.00 0 % -
462. Construction of RCC Bridge over river Dhanai at ch. 6.60 Km on Champaknagar – Mandai road (ODR) 16/02/2010 321.34 115.68 0.00 0 % -
463. Construction of RCC Bridge over Dhuraicherra at Ch. 0.90 Km on Kamalpur – Bilascherra road (ODR) 16/02/2010 297.30 262.32 262.32 100 % -
464. Construction of RCC over local stream at Ch. 12.00 Km on Mohanpur - Simna Road (ODR) 16/02/2010 232.78 83.80 0.00 0 % -
465. Construction of RCC Bridge over Kalapaniacherra at Ch.0.50 Km on Satchand Block office – old Manubankul road 09/03/2010 265.60 191.24 95.62 50 % -
466. Construction of RCC bridge over Lohar on Berimura – Taltala Road 09/03/2010 229.33 165.12 82.56 50 % -
467. Construction of RCC Bridge near causeway at Krishnapur over Balucherra at Ch.6.05 km on Maharani- Tulashikhar road 09/03/2010 178.14 128.26 64.13 50 % -
468. Construction of RCC bridge over Laxmicherra river at Ch.12.01 Km on Khowai – Udna road 29/03/2010 215.69 190.31 190.31 100 % -
469. Construction of RCC Bridge over Lohar at Ch. 0.45 Km on Kamlaghat – Gamchakobra – Banikya Chowmuhani road 09/03/2010 266.38 191.80 95.90 50 % -
470. Construction of RCC Bridge over local stream at Ch. 14.60 Km on Mohanpur – Simna road 19/04/2010 177.35 127.68 63.84 50 % -
471. Construction of RCC Bridge over Ghoramaracherra on NH-44 at Jirania Tripura Engineering College – Chalkbasta 19/04/2010 310.82 111.89 111.89 100 % -
472. Construction of RCC Bridge over Baradupatacherra at Ch.2.80 Km. on Kanchanpur – Jalabassa road (ODR) 19/04/2010 387.62 139.54 0.00 0 % -
473. Construction of RCC Bridge over Ujan Machmaracherra at Ch.9.00 Km. on Kanchanpur – Jalabassa road (ODR) 19/04/2010 307.01 110.52 0.00 0 % -
474. Construction of RCC Bridge over Champakcherra at Ch.18.40 Km. on Mohanpur - Simna road (ODR) 19/04/2010 283.82 204.34 102.17 50 % -
475. Improvement of Mailak-Gamukabari via Burbaria (7.50Km) in Tripura 23/12/2010 1068.05 769.00 384.50 50 % -
Total for Tripura (28 Projects) 29631.99 24019.62 20566.00    
GRAND TOTAL (522 Projects) 437535.52 296464.17 221033.56    

 