Development of Hydro Power

Hydro Electric Potential Development in NER & Sikkim


(Installed Capacity - Above 25 MW)

 

(Source: Ministry of Power)
As on March, 2012

 

Hydro Electric Potential Development in NER & Sikkim
Region/ State Identified Capacity(MW) as per reassessment study Capacity Developed Capacity under construction  Capacity Developed + Under Development Capacity yet to be developed
  Total  Above 25 MW (MW) % (MW) (%) (MW (%) (MW) %
Sikkim 4286 4248 570 13.42 2421 56.99 2991 70.41 1257 29.59
NORTH EASTERN REGION
Meghalaya 2394 2298 198 8.62 124 5.39 322 14.01 1976 85.99
Tripura 15 0 0 0.00 0 0.00 0.0 0.00 0.0 0.00
Manipur 1784 1761 105 5.96 0 0.00 105 5.96 1656 94.04
Assam 680 650 375 57.69 0 0.00 375 57.69 275 42.31
Nagaland 1574 1452 75 5.17 0 0.00 75 5.17 1377 94.83
Ar.Pradesh 50328 50064 405 0.81 2710 5.41 3115 6.22 46949 93.78
Mizoram 2196 2131 0 0.00 60 2.82 60 2.82 2071 97.18
Sub Total (NER) 58971 58356 1158* 1.98 2894 4.96 4052 6.94 54304 93.06

 

*  including one unit of Myntdu commissioned in Nov., 2011

 

Page Maintained By: 
infrastructure, Director