Hydro Power Projects

(Source: Ministry of Power)

 

Steps/ Measures Taken by The Govt. To Exploit Untapped Hydro Electric Potential in NE Region

 

The steps/ measures taken by the Govt. to give boost to the development of the balance hydro potential in the region are discussed below:

 

A. Policy Measures:

  1. Policy on Hydro Power Development, 2008 was notified by Govt. of India on 31.3.2008 which aimed to provide level playing field to private developers and also provided for a transparent selection criteria for awarding sites to private developers and also for provision of merchant sales of upto a maximum of 40% of the saleable energy. Some of the clauses of the above Policy on Hydro Power Development, 2008, as listed below, have been recently modified:

     

    1. The cost plus tariff regime (in which tariff is to be determined by the regulator under section 62 of Electricity Act, 2003) has been extended for public as well as private sector hydro power projects up to December, 2015.
    2. In order to enable the project developer (public as well as private sector hydro developers) to recover the costs incurred by him in obtaining the project site, as mentioned in para (a) above, he would be allowed a special incentive by way of merchant sales of up to a maximum of 40% of the saleable energy.  Projects that do not conform to the prescribed time lines would however lose this incentive of merchant sales in a graded manner. With a view to ensure timely completion of these projects, delays of every six months in the commissioning date would result in reduction of merchant sales by 5%.  This condition would be operationalised by the appropriate regulator duly apportioning the Annual Fixed Charge accordingly.
  1. National Water Policy was notified by the Govt. earlier in the year 2002 which stipulated that in the planning and operation of system, water allocation priority should broadly be in the order of drinking water, irrigation, hydro power, ecology, agro industries and non agriculture industries, navigation and other uses. The policy is being proposed to be revised. For that purpose, Govt. has prepared a Draft National Water Policy in 2012.
  2. Mega Power Projects Policy has been revised, as per which the minimum qualifying capacity of thermal power plants to avail mega project benefits, has been reduced from 1000 MW to 700 MW in certain special category States of J&K, Sikkim and the seven states of North East. The corresponding qualifying threshold capacity for hydro power plants located in the states of J&K, Sikkim and the seven states of North East, for availing mega benefits has been reduced from 500 MW to 350 MW.
  3. Constitution of Inter-Ministerial Group (IMG)
    An Inter-Ministerial Group (IMG) had been constituted by Ministry of Water Resources (MoWR) on 7th August, 2009 under the Chairmanship of Secretary (WR) on the directions of Prime Minister's Office (PMO) to evolve a suitable framework to Guide and Accelerate the development of Hydropower in the North East. Ministry of Power was also represented in the Committee. Some of the major issues/ constraints in the way of expeditious growth of hydro power development in the Region were identified by the Group like Environment & Forest Clearance including the issue of compensatory afforestation, need for infrastructural facilities like roads construction of bridges, strengthening of existing roads, efficient and reliable telecommunication links, better road transport/ air services etc., non-availability of hydrological & other data, the impact of the massive hydro power development in  Arunachal Pradesh on down-stream areas in Assam, Non-Availability of skilled man-power, Funding arrangements and Problems associated with Evacuation of Power etc. and policy interventions were proposed in its report submitted in Feb., 2010.
  4. A Task Force under the Chairmanship of Hon'ble Minister of Power with Deputy Chairman, Planning Commission, Minister of Water Resources, Minister of New & Renewable Energy, Minister of Environment & Forest and Ministers of Power from Hydro rich states has been constituted to look into all issues relating to development of Hydro Power.

B. Other Measures for timely completion of the projects:

 

In addition to the above Policy Measures, 'Other Measures' taken for ensuring the timely completion of the projects presently under construction for benefits during 11th & 12th Plan period are given below:

  1. Monitoring of Ongoing Hydro Projects :

     

    1. Advisory Group:

       

      An Advisory Group has been set up under the chairmanship of the Minister of Power to advise for expeditious completion of ongoing power generation projects.

    2. Special Monitoring Group:

       

      A special monitoring group (SMG) under the chairmanship of Secretary (Power) has been constituted to discuss & sort out various issues through video conferencing for J&K and North Eastern Region.

    3. Following mechanism is in place to monitor the progress of projects under construction:

       

      • Central Electricity Authority (CEA) is performing the duties (monitoring of the power projects) in pursuance of 73 (f) of Electricity Act, 2003. The progress of each project is monitored continuously through frequent site visits, interaction with the developers, and critical study of monthly progress reports. Chairperson, CEA holds review meeting with the developers and other stakeholders to sort out the critical issues.
      • A Power Project Monitoring Panel (PPMP) has been set up by the Ministry of Power to independently follow up and monitor the progress of the hydro projects.
      • Review meetings are taken by Ministry regularly with the concerned officers of CEA, equipment manufacturers, State Utilities/CPSUs/Project developers, etc.
  2. Monitoring of Future Hydro Projects :In addition to the Task Force which has been constituted under the Chairmanship of Hon'ble Minister of Power as mentioned above, regular meetings are taken by Chairperson, CEA to review the status of future hydro projects allotted to various developers like preparation of DPR, status of E&F clearance, likely date of placing of order etc.

For details, see below:

 

 

 

Hydropower Projects Under Construction in NER & Sikkim

 

(Source: Ministry of Power)
(as on March, 2012)

 

Hydropower Projects Under Construction in NER & Sikkim
Sl. No. Scheme State Capcity
(No. x MW)
Capacity under
Execution (MW)
Latest Commissioning
Central Sector
1. Subansiri Lower (NHPC) Arunachal Pradesh 8x250 2000 2016-17
2. Kameng (NEEPCO) Arunachal Pradesh 4x150 600 2016-17
3. Pare (NEEPCO) Arunachal Pradesh 2x55 110 2014-15
4. Tuirial (NEEPCO) Mizoram 2x30 60 2015-16
  Sub- total (Central Sector):     2770  
State Sector
5. Myntdu * Meghalaya 2x42+1x42 126 2011-13
6. New Umtru Meghalaya 2x20 40 2014-15
  Sub- total (State Sector):     166  
Private Sector
7. Chujachen Sikkim 2x49.5 99 2013-14
8. Teesta St. III Sikkim 6x200 1200 2013-15
9. Teesta St. VI Sikkim 4x125 500 2015-16
10. Rangit-IV Sikkim 3x40 120 2014-15
11. Jorethang Loop Sikkim 2x48 96 2014-15
12. Bhasmey Sikkim 3x17 51 2014-15
13. Tashiding Sikkim 2x48.5 97 2014-15
14. Dikchu Sikkim 3x32 96 2015-16
15. Rangit-II Sikkim 2x33 66 2016-17
16. Rongnichu Sikkim 2x48 96 2015-16
  Sub- total (Private Sector):     2421  
  Total:     5357  
   
In addition to the above, EPC Contract for Lower Demwe HE Project (5x342+1x40 = 1750 MW) in Arunachal Pradesh being implemented by ADPPL in Private Sector has been awarded but due to pending Forest clearance work has not yet started.
* - One unit Commissioned in Nov. 2011

 

Hydropower Development in Arunachal Pradesh

 

(Source: Government of Arunachal Pradesh)
(as on April, 2012)

  1. The Government of Arunachal Pradesh has so far allotted about 140 hydropower projects with the total installed capacity (IC) of 41500 MW that is to be developed on various rivers, rivulets and nalas in 7 major river basins:

     

    1. Tawang
    2. Kameng
    3. Dikrong
    4. Subansiri
    5. Siang
    6. Dibang
    7. Lohit
  2. Status:

     

    1. 44 are of more than 100 MW each accounting for about 37, 000 MW (90% of the total allotted IC).
    2. 1 commissioned & running - Ranganadi (405 MW) implemented by NEEPCO.
    3. 3 under implementation – Lower Subansiri (2000MW), Kameng (600MW) and Pare (110MW).
    4. 9 projects (10575MW) – techno-economic clearance issued.
    5. 12 projects (11202MW) - DPRs submitted to CEA.
    6. About 50 projects are of the capacity between 25 MW and 100 MW.
    7. Another 50 projects approximately are of less than 25 MW (about 10% of the allotted capacity).
  3. The state government regularly reviews implementation aspects of all of these projects on quarterly basis. In the review meetings senior officers from Central Electricity Authority (CEA), Central Water Commission (CWC), Ministry of Water resources and Power Grid Corporation of India Ltd (PGCIL) are also invited. In these meetings apart from review of progress the issues relating to various clearances from central government and state government organizations are also identified. Other hindrances coming / likely to come in the way of these projects are also taken into account and help is extended to the power developers to overcome those impediments.
  4. For state level clearances a single window clearance committee has been set up under the chairmanship of Chief Secretary that meets regularly and cases are cleared in the shortest possible time.
  5. As a result of all these mechanisms set in place the projects are advancing ahead for their implementation. There are inordinate delays in environment clearance and forest clearance.

Status of Development of Hydropower Projects in Arunachal Pradesh

 

(Above 25 MW Capacity and Yet to be Taken up for Construction )

 

(as on January, 2010)

 

Hydropower Projects in Arunachal Pradesh
Sl.  No. Project Basin Agency Present Installed Capacity (MW) Date of MOU  Year of Commissioning Present Status
Central
1. Tawang-I Tawang NHPC 750 24.06.2007 2016-17 DPRs submitted in Oct,' 09 is under scrutiny for acceptance in CEA/CWC and will be cleared by March, 2010.
2. Tawang-II Tawang NHPC 1000 24.06.2007 2016-17 Project allotted with IC=750 MW.  DPR submitted in July, 09 for 1000 MW is under examination in CEA/CWC and will be cleared by March, 2010.  .
3. Kameng-I Kameng NEEPCO 1120 21.09.2006 Sep. 2017. Wildlife & Bio-Diversity Department of GoAP has expressed their inability to process the proposal regarding diversion of forest land in the Pakkel Tiger Reserve without seeking prior permission of Hon'ble Supreme Court. Matter would be taken up with the Hon'ble Supreme Court by NEEPCO for taking up the S&I work and will be cleared by March, 2010. .
4. Dibang Dibang NHPC 3000 24/6/2007 2020-21 Concurrence accorded by CEA in Jan., 2008. The E&F Clearance will be got by March, 2011.
  State/Unallocated            
5. Kapakleyak Kameng Yet to be decided 160   Yet to be allotted  Difficult access.
6. Naba Subansiri Yet to be decided 1000   Yet to be allotted  To be allotted.
7. Niare Subansiri Yet to be decided 800   Yet to be allotted  To be allotted.
8. Oju-II Subansiri Yet to be decided 1000   Yet to be allotted  To be allotted.
9. Oju-I Subansiri Yet to be decided 700   Yet to be allotted  To be allotted.
10. Siang Upper & Intermediate Siang Yet to be decided 11000   Yet to be allotted.  Feasibility Report (FR) prepared by NTPC for Siang Upper Stage-I(6000 MW) and Stage-II(3750 MW) avoiding submergence of important towns. State is yet to allot it for implementation. 
11. Jiadhal Jiadhal Brahmaputra Board 75   Yet to be allotted  DPR likely by March,2012.
12. Noa Dihing Noa Dihing Brahmaputra Board 50   Yet to be allotted  DPR likely by March 2012. Declared as National Project.
Private
13. Nykcharongchu Tawang SEW Energy Ltd. 96 21-02-2008 2015-16 S&I in progress; DPR likely by 4/'10.
14. Mago Chu Tawang SEW Energy 96 27-10-2006 2015-16 S&I in progress; DPR likely by 4/'10.
15. Nyamjungchu St-I, II & III Tawang Bhilwara Energy Ltd. 900 27-10-2006 2014-15 Projects allotted as Nyamjungchu-I (98 MW) Nyamjungchu-II (97 MW) Nyamjungchu-III (95 MW).  DPR for combined Nyamjunchu Project (900 MW) submitted to CEA  in June, '09 and under examination since. 28.8.09. ToR for EIA study has been approved. DPR will be likely cleared by March, 2010.
        27-10-2006 2014-15
        2/3/2009 2014-15
16. Rho Tawang SEW Energy 60 2/3/2009 2016-17 S&I in progress. DPR likely by 5/'11.
17. New Melling   SEW Energy Ltd. 60 10/1/2009 2016-17 S&I in  progress. DPR likely by 4/'10.
18. Tsa - Chu - II Kameng Energy Development Co. Ltd. 36 10/1/2009 2013-14 S&I for preparation of PFR under progress.
19. Kameng Dam (Bana) Kameng KSK Electricity Financing India Pvt. Ltd. 480 25-01-2007 Mar., 2017 Project allotted for 600 MW. S&I in progress, Capacity has been reduced to 480 MW. DPR likely by 12/'11.
20. Badao Kameng Coastal Projects Pvt. Ltd. 70 19-11-2008 2016-17 PFR submitted to state Government.
21. Rebby Kameng Coastal Projects Pvt. Ltd. 31 19-11-2008 2016-17 S&I for preparation of PFR under progress.
22. Para Kameng Coastal Projects Pvt. Ltd. 55 19-11-2008 2016-17 S&I for preparation of PFR under progress.
23. Talong Kameng GMR Energy Ltd. 225 24-01-2007 2015-16 Project was initially allotted as Talong for 160 MW to NEEPCO. DPR of Londa HEP submitted in Oct., 2008 & returned in Dec.2008 due to mismatch of levels.
24. Lachung Kameng Coastal Projects Pvt. Ltd. 41 19-11-2008 2016-17 S&I for preparation of PFR under progress.
25. Phanchung Kameng Indiabull Real Estate Ltd. 60 25-10-2007 Oct.,2014 DPR submitted to state and will be cleared by March 2010.
26. Dibbin Kameng KSK Electricity Financing India Pvt. Ltd. 120 25-01-2007 2014-15 Project allotted for IC=125 MW which has been revised to 120 MW. DPR cleared by CEA on 4.12.09.
27. Pichang Kameng Indiabull Real Estate Ltd. 31 25-10-2007 Oct.,2014 DPR submitted to state and will be cleared by March 2010.
28. Tarang Warang Kameng Indiabull Real Estate Ltd. 30 25-10-2007 Oct.,2014 DPR submitted to state and will be cleared by March 2010.
29. Sepla Kameng Indiabull Real Estate Ltd. 46 25-10-2007 Oct.,2014 DPR submitted to state and will be cleared by March 2010..
30. Papu Kameng Indiabull Real Estate Ltd. 90 9/1/2009 Beyond 12th Plan

Under S& I

31. Jameri Kameng KSK Energy Ventures Pvt. Ltd. 50 27/12/2007 Mar-16 DPR likely by 07/'11.
32. Nafra Kameng SEW Energy Ltd. 96 14/9/2007 2015-16 DPR submitted to CEA in July,09 has been returned in Oct., 2009. Hydrology, Civil design, installed Capacity need review.
33. Pachuk-I Kameng Energy Development Co. Ltd. 60 12/1/2008 Jan. 2016 Under survey and investigation(S&I).
34. Pachuk-II Kameng Energy Development Co. Ltd. 60 12/1/2008 Jan. 2016 Under survey and investigation.
35. Majingla Kameng Energy Development Co. Ltd. 60 12/1/2008 Jan. 2016 Under survey and investigation
36. Papu Valley Kameng Vensar Construction Co. Ltd. 35 25/11/2008 Beyond 12th Plan Under S&I
37. Kameng- II (Bharali-II) Kameng Mountain Fall India Pvt.Ltd. 600 23-11-2006 2018-19 DPR likely by Mar./'10.
38. Gongri Kameng Patel Engineering Ltd. 90 18-05-2007 May 2017 DPR submitted to CEA in Oct., 09 .Under  scrutiny in CEA/CWC.
39. Utung Kameng KSK Energy Ventures Ltd. 100 11/9/2007 2016-17 S&I to be taken up by 12/10, DPR by 12/'12.
40. Nazong Kameng KSK Energy Ventures Ltd. 60 11/9/2007 2016-17 S&I to be taken up by 12/10, DPR by 12/'12.
41. Khuitam Kameng Adishankar Power Pvt. Ltd. 29 12/6/2007 Jun,2017 DPR submitted and under examination.
42. Dinchang Kameng KSK Energy Ventures Ltd. 90 11/9/2007 March, 2017 S&I to be taken up by 12/09. DPR likely by 12/'11.
43. Saskongrong Kameng Patel Engineering Ltd. 30   2014-15 S&I in progress.
44. Par Dikrong KVK Energy & Infrastructure Ltd. 65 26-12-2007 2015-16 DPR likely shortly. EIA studies in progress.
45. Dardu Dikrong KVK Energy & Infrastructure Ltd. 60 26-12-2007 2015-16 DPR likely shortly. EIA studies in progress.
46. Panyor Dikrong Raajratna Energy Holdings Pvt. Ltd. 80 25-02-2009 Feb.2015 Under S&I
47. Turu Dikrong ECI Engineering & Const.Co. Ltd. 90 21-06-2007 2016-17 DPR likely shortly.
48. Subansiri Middle Subansiri Jindal Power Ltd. 1600 29/08/2009 Oct., 2018 DPR likely by 4/'12.
49. Jarong Siang CESC Ltd. 90 25-11-2008 Beyond 12th Plan S&I yet to be taken up by developer
50. Simang-I Siang Adishankar Power Pvt. Lid 67 6/2/2008 Feb.2016 Projects allotted as Simang-I (67 MW),  Simang-II (39 MW) & Simang-III (44 MW).  To be developed in two stages of 67 MW and 66 MW.  PFR prepared & submitted to Govt. of Arunachal Pradesh
51. Simang-II Siang Adishankar Power Pvt. Ltd 66 6/2/2008 Feb.2016
    Siang Adishankar Power Pvt. Lid 44 6/2/2008 Feb.2016
52. Barpu (Pemashelpu) Siang Raajratna Metal Industries 70 27-12-2007 2015-16 DPR likely shortly.
53. Kangtangshiri Siang Raajratna Metal Industries 35 27-12-2007 2015-16 DPR likely shortly.
54. Ropum Siang Raajratna Melal Industries 45 27-12-2007 2015-16 Project allotted for IC=40 MW. Levels being finalised. DPR for IC=45 MW is likely shortly.
55. Rego Siang Tuff Power Pvt. Ltd. 141 27-12-2007 2015-16 Project allotted for IC=70 MW.DPR likely by 2/'10 for IC=141 MW.
56. Yamne Stage-I Siang Yamne Power Private Limited 60 5/3/2008 Aug.,2015 DPR likely by Apr., 2010.
57. Yamne Stage-II Siang Yamne Power Private Limited 60 5/3/2008 Aug.,2015 DPR likely by Apr., 2010.
58. Lower Yamne Stage-I Siang Yamne Power Private Limited 50 29-11-2008 2015-16 S&I in progress.
59. Lower Yamne Stage-II Siang Yamne Power Private Limited 40 29-11-2008 2015-16 S&I in progress.
60. Tagurshit Siang L&T Power Ltd. 60 23-12-2008 Dec.2017 S&I in progress
61. Tato-II Siang Tato Hydro Power Pvt. Ltd. (Reliance Energy Ltd.) 700 22-02-2006 2016-17 DPR submitted in May, 09  returned by CEA on 04.09.09 due to inadequate geological investigations, exploring possibility of relocation of dam site, making provision of desilting chamber & review of high cost/ tariff of project.
62. Naying Siang D. S. Construction Ltd 1000 22-02-2006 2017-18 DPR likely by Jan, 2010.
63. Siang Lower Siang Jaiprakash Associates Ltd. 2700 22-02-2006 March'15 (1500 MW) 2018-19 (1200 MW) Project allotted for IC=1600 MW. Revised DPR for  2700 MW submitted in Aug., 2009.   Concurrence meeting  held on 15.12.2009. Clearance letter under issue.
64. Siyom (Siang Middle) Siang SIYOM Hydro Power Pvt. Ltd. (Reliance Energy Ltd.) 1000 22-02-2006 2017-18 DPR likely by 12/'09.
65. Pauk Siang Velcan Energy Ltd. 120 30-06-2007 (rev MOA-31-07-09) 2016 Project allotted for IC=50 MW.IC revised  to 120 MW in July09 after resolution of level interference issue.  FR is being prepared.  DPR  likely by Dec., 2010.
66. Heo Siang Velcan Energy Ltd. 210 30-06-2007 (rev MOA-31-07-09) 2016 Project allotted for IC=90 MW. IC revised to 210 MW in July09 after resolution of level interference issue.  FR is being prepared.  DPR  likely by Sept., 2010.
67. Hirong Siang Jaiprakash Associates Ltd. 500 22-02-2006 Feb.2018 Under S&I ,DPR likely to be completed by  12/09.
68. Tato-l Siang Velcan Energy Ltd. 170 30-06-2007 (rev MOA-31-07-09) 2016 Project allotted for IC=80 MW. IC revised to 170 MW in July09 after resolution of level interference issue.  FR is being prepared.  DPR  likely by Sept., 2010.
69. Hirit Siang Velcan Energy Ltd. 28 30-06-2007 Jun 2017 Project allotted for IC=84 MW. IC being revised to 28 MW. Geological issues being faced. 
70. Emini Dibang Emini Hydro Power Pvt. Ltd. (Reliance Energy Ltd.) 500 2/3/2009 2019-20 DPR likely by Mar., 2012.
71. Mihumdon Dibang Mihumdon Hydro Power Pvt. Ltd. (Reliance Energy Ltd.) 400 2/3/2009 2019-20 DPR likely by Mar., 2012.
72. Sissiri Dibang Soma Sissiri Hydro Pvt. Ltd. (Soma Enterprise Ltd.) 222 18-01-2008 Dec. 2017 DPR Submitted in January 2010 and  under examination in CEA/CWC.DPR may be  cleared by May 2010.
73. Emra-II Dibang Athena Energy Venture 390 2/2/2008 Jan.2018 Under S&I.
74. Amulin Dibang AMULIN Hydro Power Pvt. Ltd. (Reliance Energy Ltd.) 420 2/3/2009 2019-20 DPR likely by Mar., 2012.
75. Emra-l Dibang Athena Energy Venture 275 2/2/2008 Jan.2018 Under S&I.
76. Etalin Dibang Jindal Power Ltd. (JV with HPDCAPL) - Etalin H.E. Power Co.Ltd. 4000 8/12/2008 Mar., 2020 DPR likely by Mar., 2012. MOEF accorded clearance in Nov.'09 for preconstruction activities as per the provisions of EIA Notification, 2006.
77. Attunli Dibang Jindal Power Ltd. (JV with HPDCAPL) -  Attunli H.E. Power Co.Ltd. 500 8/12/2008 Mar., 2018 DPR likely by Mar., 2012. MOEF accorded clearance in Nov.'09 for preconstruction activities as per the provisions of EIA Notification, 2006.
78. Gimiliang Lohit Sai Krishnodaya Industries (P) Ltd. 99 26-02-2009 Feb.2017 S & I in progress.
79. Raigam Lohit Sai Krishnodaya Industries (P) Ltd. 96 27-12-2007 2012-13 PFR submitted.
80. Tidding-I Lohit Sai Krishnodaya Industries (P) Ltd. 98 12/12/2007 Feb.2017 Under S&I
81. Kalai-II Lohit Kalai Power Pvt. Ltd. (Reliance Power Ltd.) 1200 2/3/2009 2018-19 DPR likely by 12/'11.
82. Hutong- II Lohit Mountain Fall India Pvt. 1250 23-11-2006 Nov.2018 DPR likely by 04/'10.
83. Tidding-II Lohit Sai Krishnodaya 68 26-02-2009 Feb. 2017 Under S&I
84. Kalai-I Lohit Mountain Fall India Pvt. 1450 23-11-2006 Nov.2018 DPR likely by 07/'10.
85. Demwe(Lower) Lohit Athena Energy Venture 1750 9/7/2007 2016-17 (Demwe Lower) Project allotted as Demwe with IC=3000 MW.Being developed as two schemes namely Demwe Lower (1750 MW) and Demwe Upper (1800 MW). DPR for Demwe Lower submitted in Aug, 2009 and Concurrence accorded on 20.11.2009.
86. Demwe(Upper) Lohit Athena Energy Venture 1800 9/8/2007 July 2018 DPR for Demwe Upper to be prepared by Mar., '10.
  Total (Arunachal Pradesh): Central 5870 MW 4 Schemes  
      State 14785 MW 8 Schemes  
      Private 27512 MW 74 Schemes  
      Total: 48167 MW 86 Schemes  

 