Summary Report of DoNER Schemes, as on 31.12.2024


   
All States All Amount in ₹ Crore
S.No. Scheme All Projects Completed Projects Ongoing Projects Financial Expenditure on the Ongoing Projects till 31.12.2024 Financial Expenditure yet to be made in Ongoing Projects as on 31.12.2024
No. Approved Cost No. Approved Cost No. Approved Cost
A B C D E F G H = F - G
1 PM-DevINE 35 4857.12 2 121.21 33 4735.91 752.53 3983.38
2 NESIDS-OTRI 1564 19161.56 1146 12039.26 418 7122.30 4347.95 2774.35
3 NESIDS-ROADS 98 4851.52 28 1297.76 70 3553.75 1933.07 1620.68
4 Special Packages 110 1427.68 71 782.19 39 645.49 304.07 341.42
5 Schemes of NEC 1772 13090.52 1182 9692.37 590 3398.16 1925.14 1473.02
Total : 3579 43388.41 2429 23932.79 1150 19455.61 9262.77 10192.85