Ministry of Development North Eastern Region
Project Dashboard   

Sectorwise Summary of NESIDS-ROADS Projects, as on 30.09.2024


All Amount in ₹ Crore
S.No. Sector All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 Roads & Bridges 52 1670.32 1348.50 1214.34 22 769.18 738.25 710.29 30 901.15 610.25 504.06
2 Transport and Communication 43 2707.51 1453.94 1239.41 11 700.32 688.51 567.64 32 2007.19 765.43 671.77
Total : 95 4377.83 2802.44 2453.76 33 1469.50 1426.76 1277.93 62 2908.33 1375.68 1175.83