Ministry of Development North Eastern Region
Project Dashboard   

Overall Summary of DoNER Schemes, as on 30.04.2024


All Amount in ₹ Crore
S.No. Scheme All Projects Completed Projects Ongoing Projects Financial Expenditure on the Ongoing Projects till 30.04.2024 Financial Expenditure yet to be made in Ongoing Projects as on 30.04.2024
No. Approved Cost No. Approved Cost No. Approved Cost
A B C D E F G H = F - G
1 NESIDS-ROADS 95 4377.83 26 1229.53 69 3148.30 1601.02 1547.27
2 Schemes of NEC 1742 12974.74 1123 9354.29 619 3620.45 2068.57 1551.88
3 PM-DevINE 25 4083.33 2 556.19 23 3527.14 71.26 3455.88
4 NESIDS-OTRI 1558 22396.35 1111 11419.66 447 10976.69 4562.20 6414.49
5 Special Packages 107 1364.89 60 622.14 47 742.75 451.56 291.19
Total : 3527 45197.13 2322 23181.81 1205 22015.32 8754.62 13260.70