Ministry of Development North Eastern Region
Project Dashboard   

Sectorwise Summary of NESIDS-ROADS Projects, as on 30.04.2024


All Amount in ₹ Crore
S.No. Sector All Projects Completed Projects Ongoing Projects
No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised No. Approved Cost Financial Expenditure Amount Utilised
1 Roads & Bridges 52 1670.32 1348.50 1187.84 15 558.67 556.02 552.34 37 1111.65 792.48 635.50
2 Transport and Communication 42 2665.76 1412.19 1130.39 10 629.11 603.65 495.21 32 2036.65 808.54 635.18
Total : 95 4336.08 2760.69 2318.23 25 1187.78 1159.67 1047.55 69 3148.30 1601.02 1270.68